Proposed Timetable
Presented below is a summary of the proposed CopperCo acquisition and development timetable.
Timetable Event
Quarters
Feasibility Study
Completed April 2006
Exploration Activity
Ongoing
Detailed engineering and start of procurement
Commenced
Project finance available for drawdown
3rd Quarter of Calendar 2006
Statutory approvals received
3rd Quarter of Calendar 2006
Plant construction commences
4th Quarter of Calendar 2006
Mining operations commence
2nd Quarter of Calendar 2007
1st Copper Cathode plated
2nd Quarter of Calendar 2007
The successful completion of the project development financing and construction of the mine, process and infrastructure facilities is subject to receipt by the company of necessary statutory permits and authorities, various access agreements and completion of Native Title agreements. The expected time to conclude all of these processes is recognised in the timetable of activities tabulated above.
- Forums
- ASX - By Stock
- CUO
- copperco the next producer
CUO
copperco limited
copperco the next producer, page-8
Featured News
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
Currently unlisted public company.
The Watchlist
P.HOTC
HotCopper
Frazer Bourchier, Director, President and CEO
Frazer Bourchier
Director, President and CEO
SPONSORED BY The Market Online