Presented below is a summary of the proposed CopperCo acquisition and development timetable.
Timetable Event Quarters
Feasibility Study Completed April 2006
Exploration Activity Ongoing
Detailed engineering and start of procurement Commenced
Project finance available for drawdown 3rd Quarter of Calendar 2006
Statutory approvals received 3rd Quarter of Calendar 2006
Plant construction commences 4th Quarter of Calendar 2006
Mining operations commence 2nd Quarter of Calendar 2007
1st Copper Cathode plated 2nd Quarter of Calendar 2007
The successful completion of the project development financing and construction of the mine, process and infrastructure facilities is subject to receipt by the company of necessary statutory permits and authorities, various access agreements and completion of Native Title agreements. The expected time to conclude all of these processes is recognised in the timetable of activities tabulated above.