Hi Caredes, from the last quarterly activities report
"
Progress of the debottlenecking elements are as follows:
- The electrowinning (EW) expansion was well advanced at quarter end, and the new facility was successfully completed and handed over to the Kipoi operations team on 23 October 2016;
- The tank leach (TL) facility is expected to be completed to commence commissioning during December 2016;
- The slimes reclaim area is scheduled for completion during December with earthworks and civil works 75% and 96% complete respectively;
- The start of construction of the Tailings Storage Facility (TSF3) was delayed by pending regulatory approvals and is expected to be completed by Q2 2017 taking into account potential impacts of the wet season. However, the coffer dam (a smaller dam contained within TSF3), is nearing completion and will be available to allow commencement of production from the TL until TSF3 is completed. "
So not sure if we will get an update until it is finished sometime in December by the looks of it. Gotta just let them get on with it sometimes.
Thanks
- Forums
- ASX - By Stock
- Cu trend break?
Hi Caredes, from the last quarterly activities report " Progress...
Featured News
Add TGS (ASX) to my watchlist
Currently unlisted public company.
The Watchlist
LU7
LITHIUM UNIVERSE LIMITED
Alex Hanly, CEO
Alex Hanly
CEO
SPONSORED BY The Market Online