I posted this on the EPA thread but this should provide a rough idea. Note timeframes are those suggested by the EPA. We have just entered Stage 3 Step 1. We are now at dot point 2 of Step 1
For Stage 3ALONE, this is what VRX has to go through (all taken from the procedures manual):
Step 1: Scoping the proponent’s Environmental Scoping Document(18 weeks)
-Proponent prepares and submits draft Environmental Scoping Document. VRX has just uploaded the ESD
- EPA reviews draft ESD(5 weeks from receipt of draft ESD). VRX IS NOW HERE
- VRX has been assessed on a Public Environmental Review level so a Public review of the draft ESD is required
- EPA authorises release of draft ESD(2 weeks from receipt of accepted draft ESD)
- Public review of draft ESD(Our public review level has been set at 4 weeks)
- EPA provides summary of submissions to the proponent(2 weeks from close of public review period)
- Proponent submits revised ESD
- EPA seeks advice on draft ESD from Decision-Making Authorities
- EPA approves ESD(4 weeks from receipt of advice)
- EPA notifies proponent and publishes ESD(1 week from approval)
Step 2: Preparation of additional assessment information – Environmental Review Document(6 weeks)
EPA has requested further information on the following: social surroundings, nearest sensitive receptors, greenhouse gas figures, air quality figures, road routes and aboriginal heritage surveys over the whole area.
- Proponent carries out an environmental review and submits draft Environmental Review Documents(VRX have commenced these studies)
- EPA reviews draft ERDs(6 weeks from receipt of ERD)
- EPA accepts ERDs
- VRX has been assessed on a Public Environmental Review level so a Public review of the ERDs is required
- Public review of ERDs (Step 3)
Step 3: Public review of additional assessment information – Environmental Review Document(13 weeks)
- EPA authorises release of ERDs for public review(2 weeks from accepted ERDs)
- Proponent releases ERDs for public review
- Public review of ERDs(Our public review level has been set at 4 weeks)
- EPA provides a summary of submissions to proponent(3 weeks from close of public review period)
- Proponent prepares response to submissions
- EPA reviews response to submissions(4 weeks from receipt of response to submissions)
- EPA accepts and publishes proponent’s response to submissions
Step 4: Preparation of EPA’s draft assessment report(6 weeks)
- EPA seeks advice on potential draft conditions
- EPA prepares draft assessment report(6 weeks from start of Step 4)
Step 5: Completion of EPA’s assessment
- EPA considers the draft assessment report and any conditions
- EPA agrees to adopt the draft assessment report as the basis for the EPA’s final assessment report
- If EPA doesn't choose to adopt then the proposal goes through Step 4 again
- Forums
- ASX - By Stock
- VRX
- Daily price prediction thread
Daily price prediction thread, page-3745
-
- There are more pages in this discussion • 7,112 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add VRX (ASX) to my watchlist
(20min delay)
|
|||||
Last
2.9¢ |
Change
0.002(7.41%) |
Mkt cap ! $18.21M |
Open | High | Low | Value | Volume |
2.8¢ | 2.9¢ | 2.8¢ | $5.818K | 207.6K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
2 | 404937 | 2.8¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
2.9¢ | 22499 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
2 | 404937 | 0.028 |
7 | 1069150 | 0.027 |
2 | 310860 | 0.026 |
3 | 144995 | 0.025 |
1 | 100000 | 0.024 |
Price($) | Vol. | No. |
---|---|---|
0.029 | 22499 | 1 |
0.030 | 1697048 | 5 |
0.031 | 186660 | 1 |
0.048 | 46773 | 1 |
0.050 | 6349 | 1 |
Last trade - 15.45pm 27/09/2024 (20 minute delay) ? |
Featured News
VRX (ASX) Chart |