    Jason,

    I would be pretty sure that the project can absorb a fair delay with this particular permit.

    The Permit to Mine for example, is not due until the end of August at the earliest. This is needed to commence mine construction.

    If the DDW Permit is delayed for a month or two, I would think that the wells could be completed (whether just casing - or more) concurrently with the other mine construction projects.

    The bottom line is the DDW Permit is required with sufficient time to finalise the wells no later than the day that NRC issues the Source Materials Licence - and that is quite a way off (March 2012 at the earliest)
 
watchlist Created with Sketch. Add PEN (ASX) to my watchlist
(20min delay)
Last
11.0¢
Change
0.010(10.0%)
Mkt cap ! $350.5M
Open High Low Value Volume
10.0¢ 11.0¢ 10.0¢ $1.538M 14.43M

Buyers (Bids)

No. Vol. Price($)
4 268799 10.5¢
 

Sellers (Offers)

Price($) Vol. No.
11.0¢ 5585591 46
View Market Depth
Last trade - 16.10pm 26/07/2024 (20 minute delay) ?
PEN (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.