    This is my Guesstimation Lowkey,

    With many assumptions I come up with about 4 weeks.

    Reading the announcement, 23/09/2019 Burbanks Gold Project, Positive Scoping Study,

    Using their indicated and inferred Mineral Resource of 1.2mt @ 3.7 g/t Au for 145,700 ounces of gold.

    So with 31.1 grams per ounce we need approx. 8.4 ton to produce 1 ounce of gold.

    Using the current price, Au $2416 and a stab in the dark production cost of Approx. $1416, leaving a Nett profit of $1000 p/oz

    At $1000 per ounce nett, we would need to produce 8,000 ounces to have $8,000,000 in the future fund.

    To produce 8,000 ounces we have to mine 67,200 tons ( 8.4 x 8000 )

    According to FMR investments, Greenfield's mill page, they can churn 1,000,000 tons per annum through their plant,

    So by my calculations, that's 19,230 tons per week, 67,200 tons = 3.5 weeks.

    Production cost could be more , could be less.

    Hope this helps.






 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.