Do you know that
- CopperCo started the feasibility study in 10/04 and
*planned to complete in 11/05.
- Feasibility study actually completed in 4/06 and planned
* Detailed engineering nearing completion with procurement due to commence in May 2006.
* Finance, off-take and appointment of construction engineer to be concluded in May 2006.
- But actually the finance secured in July 2006 and the detailed engineering wasn't finished until that time.
it's intereting to see how sp moved during that period as well.
sp was ~ 20~25c (10/04) -> 14~15 (6/05) -> 15~16c (11/05) -> 30c (2/06) -> 40c (4/06) -> 35c (6/06) -> 50c (7/06)