Production at the Company’s Phu Kham Heap Leach Gold Operation (formerly known as
the Phu Bia Gold Mine) in Laos has ramped-up and reached record levels. Gold shipments
for October will total over 4,400 oz.
The strong production performance highlights the success of the strategy of seasonal
operation and production of gold during the dry season months (October through to April).
During the balance of the year irrigation is suspended and the heap leach pads are covered
with plastic. The leaching process actually continues during this period resulting in a surge
in gold production once irrigation is resumed. Maintenance work completed during the
planned shutdown period has also resulted in significantly improved in-circuit recoveries.
Pan Australian Managing Director, Mr Gary Stafford, said that under this new leaching
regime, heap leach gold production is expected to out-perform previous estimates of
3,000 oz per month between October and April.
Pan Australian plans to further grow its gold production over the next several years
focussing on organic growth within the Phu Bia Contract Area in Laos.
At Ban Houayxai, approximately 25km west of the Phu Kham Operations (Figure 1),
Pan Australian is targeting the establishment of an ore reserve that could support a stand-
alone project producing greater than 100,000 oz of gold per year with a target for first gold
pour in 2011.
Drilling at Ban Houayxai earlier this year identified broad, high-grade primary gold-silver
mineralisation beneath a zone of oxide gold mineralisation (Figure 2).
In late September, an infill drilling program commenced at Ban Houayxai. The drilling
program is targeting a steeply-dipping zone of primary gold-silver mineralisation over a
strike length of approximately one kilometre. The program comprises 20 diamond core
holes totalling approximately 6,000 metres and will infill existing drilling to a spacing of
100 metres x 100 metres.
The data will provide the basis for a resource estimate which is expected to be completed
during the March quarter 2008. Two drill rigs are currently on site with a third rmobilised. This program is scheduled to be completed by the end of this year.
- Forums
- ASX - By Stock
- PNA
- drilling commences
drilling commences, page-2
-
- There are more pages in this discussion • 11 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add PNA (ASX) to my watchlist
Currently unlisted public company.
The Watchlist
LU7
LITHIUM UNIVERSE LIMITED
Alex Hanly, CEO
Alex Hanly
CEO
SPONSORED BY The Market Online