    Good summary from GBG ann today.

    corporatefile.com.au

    What update can you give on the progress of approvals with the EPA?


    CEO Garret Dixon

    This is the other major approval that we’ve been waiting for. Again, this
    process has taken longer than we had hoped, in fact more than three years. But
    we have been working closely with the WA Government and I’m pleased to
    say the Premier himself has been taking a keen interest in our project and has
    been helping to push the process forward. The EPA Board met to consider our
    project during January and we’ve been waiting since then for their
    recommendation to be released. On our latest news, we expect their
    recommendation to be out as soon as next week or certainly within the next
    few weeks. Unfortunately it is a process that is largely out of our control, but
    we certainly see the end is in sight.

    corporatefile.com.au

    What work have you been able to undertake on the Project whilst awaiting
    these approvals? Has your broader development timetable changed as a result
    of these delays?

    CEO Garret Dixon

    While there’s been some frustration with the delays we certainly haven’t been
    idle while waiting for the approvals. We’ve been working very hard on the
    procurement of all the major long lead items and I’m pleased to say that
    process has now been completed with most orders placed. In addition to that,
    we’ve been progressing with the front end engineering design of the
    concentrator and that’s moving ahead on schedule. Some parts of that project
    have been completed and some parts will shortly be heading into detail design
    phase. We’ve also been using this time to further our negotiations on the
    infrastructure required for the project including the transmission lines, the rail
    developments and finalisation of our agreements at Geraldton Port.
    The delay with FIRB and EPA approvals – and the subsequent delays to
    getting on site to start construction – means we are now anticipating first
    hematite production in the second half of 2010 and production from the
    flagship magnetite phase in the first half of 2011.
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.