Some of the conditions are mostly relevant to the stage 2 water...

  1. 1,236 Posts.
    lightbulb Created with Sketch. 181
    Some of the conditions are mostly relevant to the stage 2 water supply. Below are the actual recommendations to the minister from the EPA.
    Note that the sad faces are just formatting from my copy/paste - not any type of emotion.


    Recommendation to the Minister:

    The Committee recommends that the appeal be allowed to the extent that the following changes to conditions be made.Current recommended condition B5-3The proponent must take reasonable steps to consult with the Yugunga-Nya People about the achievement of the outcomes in condition B3-1 and B5-1(2) and objective in condition B5-2 for the life of the proposal.Proposed condition B5-3The proponent must take reasonable steps to consult with the Yugunga-Nya People about the achievement of the outcomes in condition B1-1, B2-1, B3-1 and B5-1(2) and objective in condition B5-2 for the life of the proposal.Current recommended condition B2-3The proponent shall not commence extraction of ore within the Scenario 2 Disturbance Footprint unless the CEO confirms in writing that: (1)the proponent has undertaken a troglofauna habitat connectivity assessment in accordance with subterranean fauna technical guidance and submitted it to the CEO;Proposed condition B2-3The proponent shall not commence extraction of ore within the Scenario 2 Disturbance Footprint unless the CEO confirms in writing that: (1) the proponent has undertaken a troglofauna habitat connectivity assessment in accordance with subterranean fauna technical guidance and submitted it to the CEO and the Yugunga-Nya Native Title Aboriginal Corporation;Current recommended condition B7-1At least twelve (12) months prior to the commencement of construction activities in the Stage 2 Water Supply Area, the proponent must prepare and submit a Staged Disturbance Footprint Report to the CEO that ... Appeals Committee Report to the Minister for Environment – December 2024 3Appeal objecting to the EPA’s Report and Recommendations – Report 1755 **anintha Vanadium Project Proposed Condition B7-1At least twelve (12) months prior to the commencement of construction activities in the Stage 2 Water Supply Area, the proponent must prepare and submit a Staged Disturbance Footprint Report to the CEO and the Yugunga-Nya Native Title Aboriginal Corporation that ...Current recommended condition C1-1 The proponent must not undertake1) groundwater abstraction until the CEO has confirmed in writing that the environmental management plan required by condition B2-4 meets the requirements of conditions B2-4, C4 and C5, and incorporates the research program required by condition B6;Proposed condition C1-1The proponent must not undertake: (1) groundwater abstraction until the CEO has confirmed in writing that the environmental management plan required by condition B2-4 meets the requirements of conditions B2-4, C4 and C5, and incorporates the research program required by condition B6 and has considered the recommendations outlined in Appendix D4- B of the Environmental Review Document.
    Last edited by Ferretbreath: 15/12/24
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
(20min delay)
Last
0.8¢
Change
0.000(0.00%)
Mkt cap ! $69.07M
Open High Low Value Volume
0.8¢ 0.9¢ 0.8¢ $41.86K 5.194M

Buyers (Bids)

No. Vol. Price($)
52 13196572 0.8¢
 

Sellers (Offers)

Price($) Vol. No.
0.9¢ 10091895 16
View Market Depth
Last trade - 16.18pm 24/06/2025 (20 minute delay) ?
AVL (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.