EQN 2.86% 18.0¢ equinox resources limited.

eqn quarterly report.

  1. 97 Posts.
    this is a fantastic quartely from EQN. project still on track for comlpetion in June. i like reading this line "Concentrate deliveries to the Copperbelt smelters are then expected to commence in the third quarter of 2008." bring it on. we are so close after such a long wait!!



    Equinox Minerals Limited07 May, 2008NEWS RELEASE FROM EQUINOX MINERALSEquinox Releases Results for Quarter Ended March 31, 2008.


    HIGHLIGHTS FOR THE QUARTER

    Lumwana Commissioning Commences

    Construction highlights for the quarter include:

    ? Total construction workforce has increased to approximately 4,700 employees on-site;

    ? Pre-stripping operations of the Malundwe Stage 1 pit continued throughout the quarter with 6.692Mt of waste and 1.22Mt of sulphide ore and mineralised oxide mined to date (project to date - from the start of operations 2007) with the majority of material still being mined for construction bulk-fill activities;


    ? By quarter end all of the 27 x Hitachi EH4500 diesel/AC drive (“Euclid”) 250 tonne trucks ordered had been delivered to site. Nineteen (19) trucks have been commissioned with 8 working on the current Malundwe stage 1 pit. In addition 2 primary loading units remain operational along with all support and ancillary equipment which arrived on site. During the quarter 3 more primary loading units arrived onsite and are in various stages of assembly with all three to be commissioned in Q2-2008;


    ? Siemens electrical infrastructure for trolley and pit electrics began to arrive during the quarter and the first two bases for Trolley poles were installed;


    ? SAG and Ball mill construction activities/mechanicals are near completion with work commencing on the electrical reticulation, final electrical connections and commissioning checks on the motors and supporting control equipment;


    ? Civil activities are now all but completed, with work on the crusher top structures and completion of the last floor section of the tailings thickener outstanding;


    ? Structural steel erection is now substantially completed in most areas with secondary steel work continuing;


    ? Mechanical, piping and electrical installations continued to advance during the quarter;


    ? Town housing availability for occupancy purposes reached 350 houses; and


    ? Commissioning commenced in April 2008, with the electrification of the main Lumwana 33kV substation and completion of the raw water systems commissioning.

    Lumwana Commissioning Commences

    Commissioning of the Lumwana Copper Project has commenced 15th April, 2008, with the electrification of the main Lumwana 33kV substation. This brings power from the ZESCO substation at Lumwana, which was energized earlier this year, and reticulates the power to key substations around the Lumwana plant site and infrastructure. The substation was successfully energized with mains/grid power from ZESCO, Zambia’s national power supply authority and Lumwana power draw has commenced.

    Lumwana Raw Water Extraction Systems Commissioning Complete


    On May 5, 2008, commissioning of the Lumwana Copper Project’s Raw Water Systems was completed with the testing and pumping of the process plant raw water system reclaiming raw water from the project’s completed raw water dam. Pumping tests filled the process and raw water pond achieving design rates of 500 m3 per hour per pump station.



    LUMWANA URANIUM FEASIBILITY STUDY




    Equinox has completed a Uranium Feasibility Study (“UFS”) investigating the onsite treatment of discrete and high grade uranium mineralisation contained within the Lumwana copper pitshells.

    The UFS has confirmed the viability of onsite uranium treatment. Based upon Probable Uranium Reserves, the uranium (U3O8) production rate is expected to be approximately 2.0 million pounds per year. Copper is also recovered from the uranium ore as a copper concentrate at a grade of approximately 50% Cu, contained within 15,000 tonnes per year of concentrate.

    An Environmental Impact Assessment (“EIA”) is being finalized and is expected to be submitted to the Environmental Council of Zambia (ECZ) during May 2008, as part of the permitting process required by the Government of the Republic of Zambia.

    On the basis that government and financing approvals are received, it is envisaged that site construction activities may commence during the third quarter of 2008 with the aim of commissioning the uranium processing plant during 2010.

    EXPLORATION


    Highlights for the quarter include:

    ? The Kanga Prospect is located south of the Malundwe pit at Lumwana where mining has commenced. Subsequent to the 28 RC holes reported last quarter, the drill out program has been on–going throughout the most recent wet season, to the extent that an area of 2km EW and 1200m NS of the Kanga IP target has now been drill tested. All RC holes intersected the ore schist horizon with intercepts ranging between 5 - 25 m in width encountered at the predicted down-hole position. The southern extension of the Kanga IP target area remains open to the south.

    ? The Kababisa Prospect lies approximately 5km north of the Lumwana process plant currently under construction. This zone of mineralization has strong similarities to the nearby Malundwe orebody and consequently, a combined RC (28 holes, LUM507-509; 511-536) and diamond (2 holes LUM506 and 510) drilling program was completed. The results, whilst clearly anomalous, suggest that additional exploration to the north of the tested area is warranted, because grades and thicknesses of mineralization increase in this direction. In addition, there remains 1100m of untested IP anomaly to the north of the drill area.

    ? The Ndola West prospect is located on the Copperbelt, 320km east of Lumwana. Following up previous work at Ndola West, the Company completed an extensive RC drilling program (4475m) in late 2007 and 20 diamond core holes (1987m) during the current quarter to evaluate the oxide potential of 2km strike of the Ndola West target that has been drill tested. Assay results from the RC samples, whilst returning some good grade intercepts, were largely disappointing. The diamond drill holes were interspersed amongst the RC drill holes, and the Company is awaiting assay results of the core to confirm whether such an interpretation is appropriate. Irrespective, the target tested to date at Ndola West represents less than 15% of the available prospective strike, and planning is underway to implement drill testing of the favourable contact horizon to the north-west and in adjacent fold limbs.

    ? At Cheyeza on the Kapompo Project, 100km west of Lumwana, copper anomalism was identified in soil samples, up to 5000ppmCu peak value. This target was tested with 34 shallow, inclined RC holes which were drilled in 5 fences across the peaks of the soil anomalies. Chalcopyrite was intersected in 24 of the 34 holes drilled, although mineralization was not continuous down hole. Two diamond drill holes have been drilled in Q1-2008 to provide stratigraphic and structural information regarding the prospect.

    ? The Ngala target on the Copperbelt (Kitwe tenement) was the subject of a conceptual review of historical data. This has highlighted compelling targets for the field crews to explore during 2008.
    Equinox is expanding its exploration effort now that the Lumwana mine is nearing production so as to maintain an exploration “pipeline” of projects, and has upgraded the field teams with additional quality personnel.



    CORPORATE

    Annual General Meeting of Shareholders


    The Company will hold its annual general meeting at The Grand Ballroom on the 2nd floor of the Dominion Club located at 1 King Street West, Toronto, Ontario, Canada on May 7, 2008 at 11:00 am (Toronto/Eastern Standard Time).

    Exercising of Warrants


    Out of the 26,406,250 common share purchase warrants that were issued as part of the Company’s equity offering of units on March 6, 2007 that expired on May 6, 2008, 26,403,315 have been exercised raising total proceeds of C$60,727,624.50.

    OUTLOOK

    Equinox is progressing the Lumwana Project towards development with construction advancing on all fronts and an onsite construction work force of 4,700 employees.

    At March 31, 2008 the Company had outstanding capital commitments for the Lumwana Project of $180.8 million.

    The $582.7 million in senior and subordinated project finance has been finalized and draw downs commenced in August 2007.

    Large scale mining commenced in April 2007 at the Malundwe pit and has now reached the primary sulphide ore body, with oxide ore stockpiled for later processing. A final mining production rate of 120 million tonnes per annum (20 millions tonnes per annum of ore) is expected to be reached during the second quarter of 2008 following a period of progressive mobilization of the mining fleet.

    Plant construction is well progressed and all major items of equipment for the Lumwana Plant are now on site and installed. Completion of conveyor belts, pipe work and electrical installation is currently in progress. The raw water dam and tailings storage facility is also complete.

    The EPC Contractor advises that the Lumwana Project will reach practical completion on schedule at the end of June. The Company believes that this is achievable but recognizes that there is considerable work to complete and will continue to monitor progress. The commissioning process commenced in the second quarter of 2008. Commencement of copper production from Lumwana will then follow. Concentrate deliveries to the Copperbelt smelters are then expected to commence in the third quarter of 2008.

    Equinox has completed a UFS investigating the onsite treatment of discrete and high grade uranium mineralisation contained within the Lumwana copper pitshells. The UFS has confirmed the viability of onsite uranium treatment. On the basis of appropriate approvals commissioning of the uranium processing plant is targeted for 2010.

    Equinox plans to significantly expand exploration activities and evaluate and potentially implement opportunities at Lumwana to expand throughput, improve transport logistics and in the longer term consider the processing of concentrate on site. It will also actively monitor new project and corporate development opportunities.

    A copy of Equinox’s Q1 Financial Statements and the MD&A for will be available from May 7, 2008 at www.sedar.com, www.asx.com.au and at www.equinoxminerals.com.



    TABLE 1: EQUINOX MINERALS LIMITED
    CONSOLIDATED BALANCE SHEETS
    As at March 31, 2008 and December 31, 2007

    TABLE 2: EQUINOX MINERALS LIMITED
    CONSOLIDATED STATEMENTS OF INCOME
    As at March 31, 2008 and December 31, 2007

    TABLE 3: EQUINOX MINERALS LIMITED
    CONSOLIDATED STATEMENTS OF COMPREHENSIVE INCOME
    For the three months ended March 31, 2008 and 2007

    TABLE 4: EQUINOX MINERALS LIMITED
    CONSOLIDATED STATEMENTS OF CASH FLOWS
    For the three months ended March 31, 2008 and 2007







    On Behalf of the Board of Directors of Equinox:

    Craig R. Williams - President & Chief Executive Officer


    www.equinoxminerals.com


    Corporate
    Global Exploration
    Lumwana Project
    Reports & News
    Contact
    Recent Announcements

    Equinox Announces New Independent Director Candidates

    Lumwana Raw Water Extraction Systems Commissioning Complete

    Equinox AGM Notice and Invitation to Shareholders

    Releases Positive Lumwana Uranium Feasibility Study

    Unauthorized Sale of Shares by Merrill Lynch

    Lumwana Commissioning Commences

    Advises Forthcoming Warrant Expiry and Provides Conversion Notice to Holders

    Annual Report 2007

    Year End Results for 2007


    Releases Results for Quarter ended December 31, 2007

    Lumwana Copper Project Passes 75%Development Completion

    First Quantum Minerals Acquires of 17.27% Interest

    EQUINOX Uranium Feasibility Infill Drilling Confirms High Grade Uranium Mineralization at Lumwana

    Company achieves Financial Close on US$583.8 million Lumwana Debt Facility








    For further information, please contact:
    Craig R. Williams, President and Chief Executive Officer
    Michael J. Klessens, VP Finance and Chief Financial Officer
    +61 (0) 8 9322 3318
    [email protected]
    or Kevin van Niekerk, VP Investor Relations/Corporate Development
    +1 (416) 865 3393
    [email protected]

    For information on Equinox and technical details on the Lumwana Project please refer to the company website at www.equinoxminerals.com
    Cautionary Language and Forward Looking Statements


    This press release contains “forward-looking statements” and “forward-looking information”, which may include, but is not limited to, statements with respect to the future financial or operating performances of Equinox, its subsidiaries and their respective projects, the future price of copper and uranium, the estimation of mineral reserves and resources, the realization of mineral reserve estimates, the timing and amount of estimated future production, estimated costs of future production, capital, operating and exploration expenditures, costs and timing of the development of the Lumwana Project, the costs of Equinox’s hedging policy, costs and timing of future exploration, requirements for additional capital, government regulation of exploration, development and mining operations, environmental risks, reclamation and rehabilitation expenses, title disputes or claims, and limitations of insurance coverage. Often, but not always, forward-looking information can be identified by the use of words such as “plans”, “expects”, “is expected”, “is expecting”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates”, or “believes”, or variations (including negative variations) of such words and phrases, or state that certain actions, events or results “may”, “could”, “would”, “might”, or “will” be taken, occur or be achieved. The purpose of forward-looking information is to provide the reader with information about management’s expectations and plans for 2008. Readers are cautioned that forward-looking information involves known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of Equinox and/or its subsidiaries to be materially different from any future results, performance or achievements expressed or implied by the forward-looking information. Such factors include, among others, those factors discussed in the section entitled “Risk Factors” in the Company’s AIF. Although Equinox has attempted to identify statements containing important factors that could cause actual actions, event or results to differ materially from those described in forward-looking information, there may be other factors that cause actions, events or results to differ from those anticipated, estimated or intended. Forward-looking information contained herein are made as of the date of this document based on the opinions and estimates of management on the date statements containing such forward looking information are made, and Equinox disclaims any obligation to update any forward-looking information, whether as a result of new information, estimates or opinions, future events or results or otherwise. There can be no assurance that forward-looking information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such information. Accordingly, readers should not place undue reliance on forward looking information. Technical information in this release is summarized or extracted from the ‘‘Amended Technical Report on the Lumwana Copper Project, North West Province, Republic of Zambia’’ dated October 2006 (the ‘‘Technical Report’’), prepared by Michael Davis, Process Manager, Ausenco Ltd. (‘‘Ausenco’’), Ross Bertinshaw, Principal of Golder Associates Pty Ltd. (‘‘Golder’’), Tim Miller, Director, of Investor Resources Finance Pty Ltd (‘‘IRF’’), and Robert Hanbury, Associate Director, of Knight Piésold Pty Ltd. (‘‘Knight Piésold’’), each of whom is a ‘‘Quali?ed Person’’ in accordance with National Instrument 43-101 —Standards of Disclosure for Mineral Projects.

    Readers are cautioned not to rely solely on the summary of such information contained in this release, but should read the Amended Technical Report which is posted on Equinox’s website (www.equinoxminerals.com) and filed on SEDAR (www.sedar.com) and any future amendments to such report. Readers are also directed to the cautionary notices and disclaimers contained herein. All currency in this release is U.S. dollars unless otherwise stated.



































 
watchlist Created with Sketch. Add EQN (ASX) to my watchlist
(20min delay)
Last
18.0¢
Change
0.005(2.86%)
Mkt cap ! $22.29M
Open High Low Value Volume
18.0¢ 18.0¢ 18.0¢ $1.494K 8.3K

Buyers (Bids)

No. Vol. Price($)
1 50000 17.5¢
 

Sellers (Offers)

Price($) Vol. No.
18.0¢ 2888 1
View Market Depth
Last trade - 10.51am 15/11/2024 (20 minute delay) ?
EQN (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.