ok so were looking for
1 confirmation the archeo team submitted their report on the track survey (draft/final)
2. agreement by Heritage fold to proceed to lay track and site (presumably bypassing area where stuff found)
3. move Diamond Rig on site
4 commence drilling hole 1
5 complete holes 2 and 3
6 Start DHEM possibly on hole 1 even before holes 2-3 finished (3-5 days each hole depending on?)
I'm going to stick my neck out and say 1,2,3 will all happen rapid fire in early Jan (#1 possibly earlier) and then #4 by mid Jan. Could complete drilling #5 before end Jan then #6 DHEM can start etc. Hopefully evidence of mineralisation during drilling.
Position Held. (more than yesterday)
- Forums
- ASX - By Stock
- ERW Errawarra : The Waiting is Killing Me But Worth It
ok so were looking for1 confirmation the archeo team submitted...
-
- There are more pages in this discussion • 176 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add ERW (ASX) to my watchlist
(20min delay)
|
|||||
Last
8.6¢ |
Change
0.002(2.38%) |
Mkt cap ! $8.249M |
Open | High | Low | Value | Volume |
8.4¢ | 8.6¢ | 8.4¢ | $14.96K | 175.7K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
1 | 40000 | 8.3¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
8.7¢ | 47000 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 40000 | 0.083 |
1 | 20000 | 0.081 |
4 | 170000 | 0.080 |
2 | 30000 | 0.079 |
2 | 38461 | 0.078 |
Price($) | Vol. | No. |
---|---|---|
0.087 | 47000 | 1 |
0.092 | 87500 | 1 |
0.100 | 44424 | 2 |
0.105 | 11940 | 2 |
0.110 | 258700 | 4 |
Last trade - 11.47am 09/10/2024 (20 minute delay) ? |
Featured News
ERW (ASX) Chart |
The Watchlist
AHK
ARK MINES LIMITED
Ben Emery, Executive Director
Ben Emery
Executive Director
SPONSORED BY The Market Online