GBG 0.00% 2.9¢ gindalbie metals ltd

expansion plans and ansteel visit

  1. 20,450 Posts.
    lightbulb Created with Sketch. 269
    1
    Attention ASX Company Announcements Platform
    Lodgement of Open Briefing®
    Gindalbie Metals Ltd
    London House, Level 9
    216 St Georges Terrace
    Perth, WA 6000
    Date of lodgement: 02-Jun-2008
    Title: Open Briefing®. CEO Outlines Expansion Plans & Opportunities
    Record of interview:
    corporatefile.com.au
    Gindalbie Metals Limited (ASX Code: GBG) have commenced a Feasibility Study
    on increasing the magnetite start-up production rate of the Karara Iron Ore Project
    from 8 Mtpa (4 Mtpa concentrate and 4 Mtpa pellets) to 12Mtpa of magnetite
    concentrate. The Feasibility Study will also assess the viability of further
    increases to the magnetite concentrate production rate. How long will this take?
    Would any additional capital be required above your original BFS estimate? What
    would the likely product mix (concentrate vs. pellets) be under an expanded
    production scenario?
    CEO Garret Dixon
    You have to think about where Gindalbie came from. When we started with our
    equal joint venture partner Ansteel we thought we had a 400 million tonne
    Exploration Target at Karara and we looked at a potential mining rate of 20 Mtpa
    to provide our estimated concentrate production rate of 8 Mtpa.
    However, Karara has proven to be a much richer orebody than first anticipated
    with drilling to date defining a 497 million tonne Reserve plus a 929 million tonne
    Resource of available magnetite iron ore. We are currently drilling to define our
    magnetite Exploration Target of 2.2-2.8 billion tonnes, which would equate to 0.9-
    1.1 billion tonnes of concentrate grading 68-69% - or 1 billion tonnes of a high
    grade Direct Shipping Ore equivalent, if you like.
    As a result, our production rate could comfortably be three times the level of our
    Bankable Feasibility Study and possibly more. As a first stage, we’ve started to
    look at increasing the start-up rate to 12 Mtpa. We know that Ansteel are also
    very keen to get more ore for their own expansion plans, which involve lifting
    their finished steel production from 24 Mtpa to more than 50 Mtpa by 2011.
    2
    Any increase beyond the current 8 Mtpa of concentrate production will require
    additional capital and we’re doing the feasibility studies on the costs of the
    upgrade at the moment. We will know that by the end of the year, however
    doubling the production capacity does not mean a doubling of the original capex
    estimate. A large amount of the up-front capital for this project goes into
    infrastructure with built-in additional capacity and we will be able to utilize that
    with any expansion. As a ballpark estimate, the cost of an identical concentrator to
    the one planned, which would double production to 16 Mtpa, might cost A$600-
    800 million.
    With regard to product mix, we haven’t yet had any detailed discussions about
    what would be the future (expanded) mix between concentrate and pellet. It is no
    secret however, that pellet products are becoming increasingly valuable and that
    has been reflected in the increased prices for this product recently announced.
    corporatefile.com.au
    Under your current agreement with joint venture partner AnSteel, the Karara
    project will provide 80% of the feed to their Bayuquan steel mill in China. With
    the planned production expansion at Karara, how will the Bayuquan mill
    accommodate any additional ore? What are the options for Gindalbie as the
    Karara project ramps up to your longer-term target of +30Mtpa of iron ore
    products? What about including potential ore from sources like Lodestone?
    CEO Garret Dixon
    Last week we had the opportunity to take some brokers and analysts up to northern
    China to see first hand the AnSteel facilities; to meet Ansteel executives and to see
    the new Bayuquan steel mill. We also had the opportunity to visit a mine,
    concentrator and pellet plant similar to the facilities we’ll be building as part of the
    Karara project.
    At the port at Yingkou, AnSteel are two months from commissioning the 6.5 Mtpa
    Bayuquan steel mill. The mill’s location adjacent to the port has been purposely
    chosen to receive imported ore from Karara and AnSteel are already talking about
    further expansions to its steelmaking capacity in expectation of additional feed
    from Karara. During the broker visit, Ansteel was very open about the importance
    of Gindalbie and Karara to its own expansion plans.
    Our JV with Ansteel is just for the Karara project and excludes potential ore from
    projects like Lodestone, which we are looking at developing ourselves further
    down the track; potentially with other partners. We’d certainly talk to Ansteel but
    we’re not locked into them for Lodestone or our other tenements.
    corporatefile.com.au
    You recently announced an Exploration Target for DSO hematite of 80-100 Mt at
    59-60% Fe. Where do you see the best opportunities to expand this resource base?
    Does this mean an increase in hematite production? Is this scenario included as
    part of your current feasibility study options?
    CEO Garret Dixon
    We’ve always focused on Karara as our cornerstone project.
    We’ve also recognised that across our tenements there is significant potential for
    other production sources and opportunities, which Gindalbie can pursue in its own
    right. These include the Warriedar Joint Venture with Royal Resources which has
    revealed some promising hematite prospects.
    3
    In recognising this, we have redirected some of our internal resources toward
    accelerating development of these prospects, in particular those with capacity for
    DSO.
    We certainly have the management capability and the financial capacity to develop
    these projects in our own right without Ansteel. The Karara JV with Ansteel
    makes up only 20% of the 1900km2 of tenements Gindalbie have in the Mid-West
    region. This means there’s a lot of prospective ground out there that we have yet
    to scratch the surface of.
    Along with our magnetite expansion plans, we are currently examining the
    potential to increase hematite production from Mungada from an initial 2 Mtpa
    DSO in 2009 to 3 Mtpa. None of the hematite resource development work we’re
    doing outside the Karara JV area is part of any current feasibility study.
    corporatefile.com.au
    With Gindalbie’s available capacity at Geraldton port around 14Mtpa, can you still
    use the Geraldton port with an expanded production footprint? Do you plan to
    utilise future capacity at the yet to be constructed Oakajee port?
    CEO Garret Dixon
    We are certainly working very closely with the Geraldton Port Authority toward
    realising our first production goals in 2009 for hematite and 2010 for magnetite.
    This can be comfortably accommodated within the existing infrastructure
    framework and is the best way we can get our product to market.
    To realise the full potential of the Karara project - under an expanded production
    scenario - we would need to access the planned Oakajee port. We have spoken to
    the consortiums involved with its development and we strongly support them both.
    Our intention is to move at least 15 Mtpa through Oakajee port and we’re doing
    everything we can to make sure Oakajee goes ahead as we believe it’s the right
    solution for development of the mid-west region as the next iron ore province in
    Australia.
    corporatefile.com.au
    In a recent presentation you revealed the dollar value of magnetite net to Gindalbie
    was more than 28 times that of hematite. Why don’t you just focus on growing
    your magnetite resource?
    CEO Garret Dixon
    Our magnetite resource is the largest JORC iron ore resource in the Mid-West and
    will underpin a long-term project commitment to the area. Having a standalone
    hematite resource allows us to get it to market quicker and importantly realise that
    early cashflow. For Gindalbie, hematite is a low capital project we can do in our
    own right and one that generates significant value for our shareholders.
    There are different markets available for magnetite and hematite products. Our
    Karara JV with Ansteel is particularly important as it is underpinned by long term
    offtake agreements. Along with magnetite, Gindalbie has significant opportunity
    to take advantage of the current demand strength in the iron ore market and our
    extensive tenement holdings to develop our hematite resource at the same time.
    4
    corporatefile.com.au
    This next question is for Gindalbie’s new Chief Financial Officer, David Southam.
    You have finalised an equity funding package with Ansteel for a total of A$534
    million, which represents 30% of the combined Mungada and Karara project
    forecast capital cost of A$1.8 billion. What are your outstanding repayment
    obligations? When do you expect to make a decision regarding Gindalbie’s
    funding obligations for the balance of the project’s capex? What are your
    financing options?
    CFO David Southam
    AnSteel have made two subscription payments toward the project to date totalling
    A$105 million and has remaining payments of A$267.06 million to earn its 50%
    stake in the project. Under our development obligations, Gindalbie has two
    contributions to make; one in July of A$18.38 million and the second in October
    for A$143.68 million. The difference between the two payments is effectively part
    of AnSteel’s buy-in cost. Other things Ansteel has to contribute to earn its share is
    underwriting the project debt and providing product offtake.
    Also, under the terms of the Karara Joint Venture Development Agreement,
    Gindalbie can request Ansteel to provide debt finance for its share of equity
    contributions to the Project. We have commenced discussions with Ansteel
    around provision of that debt funding for Gindalbie’s equity on similar terms to
    the overall project funding, which we’re finalising with China Development Bank.
    corporatefile.com.au
    Can you give us an update on the status of the Public Environmental Reviews for
    both Mungada and Karara?
    CEO Garret Dixon
    We’re a long way down the track with obtaining the environmental approval for
    both the hematite and magnetite stages of the Karara Project. We expect approval
    of the hematite project later this year. Our magnetite approvals are also on track
    with a submission of our final PER to the EPA early next month with approvals
    expected in early 2009.
    Some time ago, the West Australian government instigated the Mid-West Review
    to look at the various iron ore projects in the region. The main aim of the review
    was to ensure that these projects could proceed. In that review, it was noted that
    with Karara, the Government was pre-disposed for the approval of the magnetite
    project as it delivers significant benefit to the State. However, the Government
    indicated reservations about some of the hematite proposals.
    The smaller hematite start-up phase of Karara is made up of deposits located on
    both the Karara and nearby Mungada tenements and as we have previously pointed
    out the tenements which cover the Mungada Ridge present some environmental
    challenges. We are working with the Government agencies on the best way
    forward but it may be a case of reaching some sort of compromise regarding those
    hematite deposits contained within the Mungada Ridge, at least while further
    studies of the biodiversity of the area are conducted.
    What we are quite confident of is that this will not affect our plans to have a startup
    hematite operation in 2009 at Karara, or our planned production level of 2-3
    Mtpa. As I pointed out earlier, we also have an aggressive exploration program
    for DSO hematite across all our tenements with significant targets and we are very
    confident more than replacing any resources that we may temporarily suspend.
    5
    corporatefile.com.au
    What are the immediate priorities for Gindalbie?
    CEO Garret Dixon
    We continue to work very hard on the engineering side of the project and have
    already started the process for ordering long lead items such as ball mills and
    crushers. Our attention is also focused on continuing our work toward securing
    environmental approvals as well as finalising the project debt arrangements of
    China Development Bank. Whilst we have existing agreements for Ansteel to take
    all the offtake at market rates for the project, we are also finalising the indices to
    be used for those market rates and we should be able to do this shortly after the
    current ore price negotiations have settled. It certainly looks as though the 2008
    ore price increase will be somewhere between 65% and 85%, which augurs very
    well for our project and the returns going forward.
    corporatefile.com.au
    Thank you Garret & David.
    For further information on Gindalbie Metals Limited visit www.gindalbie.com.au
    or call Garret Dixon or Michael Weir on +61 8 9480 8700.
    To read other Open Briefings, or to receive future Open Briefings by email, please
    visit www.corporatefile.com.au.
    DISCLAIMER: Corporate File Pty Ltd has taken reasonable care in publishing the information contained in this Open
    Briefing®. It is information given in a summary form and does not purport to be complete. The information contained is not
    intended to be used as the basis for making any investment decision and you are solely responsible for any use you choose
    to make of the information. We strongly advise that you seek independent professional advice before making any
    investment decisions. Corporate File Pty Ltd is not responsible for any consequences of the use you make of the
    information, including any loss or damage you or a third party might suffer as a result of that use.
    COMPETENT PERSON COMPLIANCE STATEMENT: The information in this document that relates to Exploration Results,
    Mineral Resources or Ore Reserves is based on information compiled by Mr Andrew Munckton who is a Member of the
    Australasian Institute of Mining and Metallurgy. Mr Munckton is a full-time employee of the Gindalbie Metals and has
    sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the
    activity which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the Australasian Code
    for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr Munckton consents to the inclusion in the
    presentation of the matters based on his information in the form and context in which it appears.
    JORC – EXPLORATION TARGETS: It is common practice for a company to comment on and discuss its exploration in
    terms of target size and type. The information relating to exploration targets should not be misunderstood or misconstrued
    as an estimate of Mineral Resources or Ore Reserves. Hence the terms Resource(s) or Reserve(s) have not been used in
    this context. The potential quantity and grade is conceptual in nature, since there has been insufficient work completed to
    define them beyond exploration targets and that it is uncertain if further exploration will result in the determination of a
    Mineral Resource.
    Karara Hematite
    Reserve Classification Mt Fe % SiO2 % Al2O3 % P % LOI
    Probable Reserve 10.9 61.7 6.0 2.2 0.10 3.5
    Resource Classification Mt Fe % SiO2 % Al2O3 % P % LOI
    Indicated 6.9 62.5 5.2 1.4 0.13 2.7
    Inferred 9.3 61.1 6.3 3.0 0.12 4.3
    Subtotal 16.2 62.0 5.6 2.0 0.12 3.3
    Note: 1. The reserve was defined to provide sufficient material from the indicated resource material to support a minimum of 6 year
    mine life.
    2. Resources are exclusive of Reserves
    Karara Magnetite
    Reserve Classification Mt Fe % SiO2 % Al2O3 % P % LOI
    Probable 497 36.3 42.71 0.89 0.089 -0.74
    Resource Classification Mt Fe % SiO2 % Al2O3 % P % LOI
    Indicated 158 36.4 42.65 0.82 0.091 -0.69
    Inferred 771 36.2 42.76 0.94 0.087 -0.79
    Subtotal 929 36.3 42.71 0.89 0.089 -0.74
    Note: 1. The reserve was defined to provide sufficient material from the indicated resource material to support a minimum of 6 year
    mine life.
    2. Resources are exclusive of Reserves
 
watchlist Created with Sketch. Add GBG (ASX) to my watchlist

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.