First drill hole (of the planned 25 holes) was reported June 16, with 2nd hole in progress at that time.
In the first assay announcement on July 29 they had completed 7 holes, so at that rate each hole had been taking about a week, and they should probably have drilled 10 or 11 holes by now.
Given this rate of progress I’m hopeful that we might see another batch of assays reported this coming week.
I originally thought that the drilling campaign would go faster than this and that we’d have almost completed the 25 holes by now, but I think that was assuming they’d have 2 rigs operating, and of course the shortage of cash has meant only 1 rig
- Forums
- ASX - By Stock
- Exploration drilling
AGR
aguia resources limited
Add to My Watchlist
4.17%
!
2.5¢

First drill hole (of the planned 25 holes) was reported June 16,...
Featured News
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
|
|||||
Last
2.5¢ |
Change
0.001(4.17%) |
Mkt cap ! $37.04M |
Open | High | Low | Value | Volume |
2.5¢ | 2.5¢ | 2.5¢ | $58.78K | 2.351M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
4 | 778127 | 2.4¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
2.5¢ | 108000 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
4 | 778127 | 0.024 |
2 | 249692 | 0.023 |
2 | 952821 | 0.022 |
5 | 1398260 | 0.021 |
9 | 512000 | 0.020 |
Price($) | Vol. | No. |
---|---|---|
0.025 | 108000 | 1 |
0.026 | 230000 | 2 |
0.027 | 496502 | 2 |
0.028 | 1000000 | 1 |
0.029 | 745000 | 2 |
Last trade - 14.12pm 10/09/2025 (20 minute delay) ? |
Featured News
AGR (ASX) Chart |
The Watchlist
EVR
EV RESOURCES LTD
Shane Menere, Non-Executive Chairman
Shane Menere
Non-Executive Chairman
SPONSORED BY The Market Online