RHM richmond mining limited

Feasibility StudyDuring the quarter, the Company continued the...

  1. 1,939 Posts.
    lightbulb Created with Sketch. 290
    Feasibility Study

    During the quarter, the Company continued the feasibility study which, whilst an accelerated
    timetable, is scheduled for completion by the end of the March quarter 2011.

    GR Engineering Services, a leading and well respected engineering firm in Perth, is
    managing the feasibility study with assistance in the United States by a civil engineering
    firm from Reno, Nevada.

    Along with existing permitting, environmental, water, geological, rail and port consultants,
    the Company has engaged leading consultants in the respective fields of resource
    estimation, geotechnical assessment, mining engineering and rail siding and load out facility
    design work to assist with the feasibility study.

    The Buena Vista feasibility study is premised on accessing ore solely from the West deposit
    on the following parameters:
    ?
    A base mine life for Stage 1 of around 10 years;
    ?
    An annual mining rate of approximately 3.5 Mtpa ? 4.0 Mtpa of ore;
    ?
    A crushing rate of approximately 600 tph and plant throughput rate of approximately
    400 tph;
    ?
    An annual concentrate production rate of up to 1.5 Mtpa; and
    ?
    A final concentrate grading +66% total Fe.

    Mine planning and production scheduling has commenced.

    Geotechnical investigations are nearing completion.

    All site infrastructure investigations are proceeding satisfactorily
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.