I left site 4 weeks ago and there was a very small stock pile approx 3m round and 2 meter high - there is a lot of start up issues the plant can only put out 25 tonne an hour, but was not running very well, so for a 10,000 tonne first shipment = 16days running time
My friend who is on site says there running more then not now but still teething issues
I will find out if any trucks have left but I would doubt it I have heard December for shipment more like end of December I would think.
The float circuit number 1 will not be complete to the new year .
The second float circuit foundation has started but there is 2-3 months or civils works first.
The float circuit improves the grade
As well there is a ball mill going in -6 months off plus commissioning to reduce the size of ore to help separation of the product
- Forums
- ASX - By Stock
- First export
I left site 4 weeks ago and there was a very small stock pile...
-
-
- There are more pages in this discussion • 225 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add NMT (ASX) to my watchlist
|
|||||
Last
8.8¢ |
Change
0.007(8.64%) |
Mkt cap ! $54.84M |
Open | High | Low | Value | Volume |
8.1¢ | 9.1¢ | 8.1¢ | $96.17K | 1.146M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
1 | 10150 | 8.3¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
8.8¢ | 24917 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 10150 | 0.083 |
3 | 115500 | 0.082 |
4 | 285577 | 0.081 |
9 | 747124 | 0.080 |
1 | 11500 | 0.079 |
Price($) | Vol. | No. |
---|---|---|
0.090 | 24917 | 1 |
0.091 | 5250 | 1 |
0.093 | 12000 | 1 |
0.096 | 82000 | 1 |
0.100 | 22672 | 4 |
Last trade - 16.10pm 12/07/2024 (20 minute delay) ? |
Featured News
NMT (ASX) Chart |