Assuming
1. The Berge Helene leaves Singapore at the End of August as per schedule with all systems pre-commissioned. (It is currently ahead of schedule)
2. 6-8 weeks to get to location
3. 3-5 days to connect anchors
4. 2 weeks to connect production, water and gas injection lines and control lines.
Then initial prodcution in December is definitely achievable.