    Geodynamics is pleased to announce that Habanero 3 well was first opened under
    controlled flowing conditions on Friday 14 March 2008. The well cleaned up rapidly
    from drilling mud and assumed relatively constant output. The well is sustaining
    production of 18 kg/second at a flowing pressure of 27.5 MPa (3,990 psi) through a
    12.5mm fixed choke. Current flowing temperature is 208 °C. The flow is directed to
    a steam separator designed for up to 25 kg/second input. A variable choke capable
    of increasing production is available for trim (finely adjust the flow rate). In one short
    experiment lasting 3 minutes the variable choke was opened to 100% and production
    of 40 kg/second was sustained over that period.
    Productivity is 400% higher than that obtained from Habanero 2 in 2005 (at its higher
    rate) where lost down-hole equipment impeded flow and eventually caused blockage
    from the main fracture zone.
    During production and shut-in of Habanero 3, the monitored well head pressure at
    Habanero 1 responded as expected, indicating good communication between the
    wells at 4,250m depth.
    The flow testing of Habanero 3 will shortly be followed by combined flow from
    Habanero 3 and re-injection into Habanero 1. On Sunday the high pressure pumps
    required for the re-injection arrived on site.


    The Company envisages making a further announcement in approximately one week
    on the progress of the circulation test.
    Jolokia 1 update
    The spud of Jolokia has been delayed due to difficulties re-commissioning the top
    drive system after a warranty replacement of the top drive, its associated carrier
    assembly and service umbilicals. Geodynamics is working to resolve the problems
    with the equipment manufacturer, LeTourneau and with the assistance of our lead
    contractor Easternwell. It is currently anticipated that these equipment issues should
    be rectified by Wednesday 19 March.

    Jolokia 1 is located approximately 9km from Habanero and is targeting fractured
    granites at a similar depth known to be 10°C hotter than the Habanero wells.
 
watchlist Created with Sketch. Add RNE (ASX) to my watchlist
(20min delay)
Last
0.6¢
Change
0.001(20.0%)
Mkt cap ! $4.356M
Open High Low Value Volume
0.6¢ 0.6¢ 0.6¢ $61 11.07K

Buyers (Bids)

No. Vol. Price($)
5 1025823 0.5¢
 

Sellers (Offers)

Price($) Vol. No.
0.6¢ 7285048 11
View Market Depth
Last trade - 16.10pm 09/07/2024 (20 minute delay) ?
RNE (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.