    GGP Fracture plans to start this week and could take
    only 7 - 10 days to complete with oil flowing

    A similar procedure and location as GGP is about to start with TEX stating a similar time of 7-10 days.

    The SRH-C # 6H well, the first well in a back to back two well program is being readied for fracture
    stimulation and testing.
    Halliburton will be running the fracture stimulation program which is planned
    to start later this week. The current plan has us stimulating seven intervals, primarily in the lower
    Wolfcamp sections.


    Today TEX announced ...

    Wolfberry Frac program will involve stimulation of 11 seperate stages from 1,874m to 2,987 m and will take two to three days to complete .
    then a temporary plug will be set at the top of the wolfberry section immediatley after the completion of the frac program .

    it is expected that the combined process will take 7 to 10 days.

 