Hmm, Couple of interesting points of information contained in here.
The following jumped out the most,it's some of G Sloane's KPI targets relating to Roseby.
"1,000,000 options exercisable at 15 cents and expiring 30 June 2013, vesting on commencement of on-site construction at Roseby by no later than 1 December 2008"
and
"1,000,000 options exercisable at 15 cents and expiring 30 June 2013, vesting on satisfactory commissioning of the Roseby treatment plant at a rate of at least 90% of its rated capacity by no later than 31 March 2010, In addition a cash payment of $100,000 on satisfactory commissioning of the Roseby treatment plant at a rate of at least 90% of its rated capacity by no later than 31 March 2010."
These are more specific dates/targets than the company have released lately. At least i've got something to measure them against now.