From: Elizabeth Gerrard...

  1. 198 Posts.
    From: Elizabeth Gerrard [[email protected]]
    Sent: Friday, 23 October 2009 12:52 PM
    To: @
    Cc: Jane Lowe
    Subject: FW: ASX ANNOUNCEMENT 20 OCTOBER 2009

    Hello *

    Thank you for your email regarding the forward work program announcement.

    The Habanero 3 well will not be operating in the near future as it is damaged and was pumped full of mud to stop the flow. The insurance claim is still being processed, but once the claim is approved we expect to drill a replacement well at Habanero. I do not have a time frame for this but expect it may be considered by the Joint Venture partners after the program of work at Jolokia is completed. The forward work program announcement indicates we will drill doublets (two wells) after Jolokia, but does not specify a location as this has not been worked out yet.

    We are now looking at the costs involved in relocating the 1 MW power plant from Habanero to another site on our tenement or whether it is more economical to to build a new power plant. The reasoning behind relocating the plant is that there are long lead and delivery times to be considered in re-ordering plant components to build another power plant at Jolokia or Savina. While these components are already available and not being used at the operations, it may be cheaper to move the components to another location. This will require rework but may be faster and cheaper. No decision has been made by the JV partners about the 1 MW plant.

    In order to demonstrate that we have the resources required to fuel a commercial scale demonstration plant, we must demonstrate that we can access flowing fractures in other parts of our tenement. For this reason we are returning to Jolokia to hydraulically stimulate the granite and increase the size of the small fracture intercepted there during drilling. This program of work will commence in 2010 after we have completed the well - that is to insert a new casing tube the length of the well to ensure reservoir fluid does not come into contact with the existing casing which is the same as that used in Habanero 3. This new casing will mean the well is thinner but still able to be used as either an injection or production well.

    I understand that the announcement did not meet your information needs and I have included your comments in feedback to management. We are preparing the text for the September Quarterly Report and will aim to provide more detail about Habanero 3 and the plant in this document.

    Thank you for taking the time to email us and please feel free to call me if you would like to talk about our program more.

    Regards

    Elizabeth Gerrard
    Investor Relations & Public Relations Manager

    Geodynamics Limited
    Level 2 23A Graham Street
    PO Box 2046 Milton QLD 4064 Australia
    Tel +61 7 3721 7504 fax +61 7 3721 7599
    Email [email protected] Web www.geodynamics.com.au


    -----Original Message-----
    From: * [mailto: @]
    Sent: Wednesday, 21 October 2009 9:01 PM
    To: Cassandra Strike
    Subject: ASX ANNOUNCEMENT 20 OCTOBER 2009

    Hello :)

    This enquiry is about the announcement dated:

    20-Oct-2009
    "Project Update - Forward work program Innamincka Joint Venture"

    There is no mention of Habanero-3.

    What is the situation regarding Habanero-3 ?

    Thanks !


    ______________________________________
    This Email is intended for the use of the addressee and may contain information that is privileged and confidential. If you are not the intended recipient you are hereby notified that any use, dissemination, distribution or reproduction of this email or the contained information is strictly prohibited. If you have received this email in error, please notify the sender by return email and destroy all copies of the original message.

    Except as required by law, Geodynamics Limited does not represent, warrant and/or guarantee that the integrity of this email has been maintained nor that the communication is free of errors, virus, interception or interference.
    ________________________________________

 
watchlist Created with Sketch. Add RNE (ASX) to my watchlist
(20min delay)
Last
0.6¢
Change
0.002(50.0%)
Mkt cap ! $4.356M
Open High Low Value Volume
0.5¢ 0.6¢ 0.5¢ $1.817K 336.2K

Buyers (Bids)

No. Vol. Price($)
3 599402 0.5¢
 

Sellers (Offers)

Price($) Vol. No.
0.6¢ 4849364 8
View Market Depth
Last trade - 16.10pm 11/07/2024 (20 minute delay) ?
RNE (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.