Thanks Doggo for taking a look and reporting.
We are supposed to be 6 weeks to continuous 24hr MgO production.
Maybe they were out inspecting potential sites for stage 2, or maybe the contractors are waiting to be paid before they return.
Maybe they are waiting for the additional instrumentation to arrive.
Remaining tasks to get the Demo plant going included:
- Spray Roaster insulation works – in progress
- Spray Roaster Ladder Modifications – in progress
- Agitator replacement and optimisation – delivery due end of August / early September
- Process Control Software Updates – mobilisation planned for August / early September
- Additional instrumentation installation and equipment upgrades to enhance operability – delivery due end of August / Early September
Oh, yes, and they need to hire or contract 3 shifts to run the plant by October - not sure if "by October" means 1st week or last week, so I'll say mid month which makes it 6 weeks.
- Forums
- ASX - By Stock
- LMG
- general discussion
general discussion, page-2233
-
- There are more pages in this discussion • 166 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add LMG (ASX) to my watchlist
(20min delay)
|
|||||
Last
2.6¢ |
Change
0.001(2.00%) |
Mkt cap ! $58.71M |
Open | High | Low | Value | Volume |
2.6¢ | 2.6¢ | 2.5¢ | $31.18K | 1.240M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
1 | 455568 | 2.5¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
2.6¢ | 147515 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 455568 | 0.025 |
3 | 315333 | 0.024 |
1 | 100000 | 0.023 |
3 | 329000 | 0.022 |
2 | 1076190 | 0.021 |
Price($) | Vol. | No. |
---|---|---|
0.026 | 147515 | 1 |
0.027 | 11150 | 2 |
0.028 | 21512 | 2 |
0.029 | 105585 | 3 |
0.030 | 208406 | 2 |
Last trade - 13.23pm 05/11/2024 (20 minute delay) ? |
Featured News
LMG (ASX) Chart |