    Our CEO should be at the coalface in Thailand for at least the next seven weeks to make sure production deadlines are met in order to repay Nebari on 19th June - for that to happen then:
    1)The high grade ore from the pods need to be fed to Plant#2 starting before the end of Feb for a period of up to 6 weeks,
    2)The old stockpile ore needs to be fed to Plant#1 by very early March to start the one month commissioning stage.
    3)There must be enough regular ore mined by early April to continuously fill both plants.
    I'd strongly suggest forgetting Miami next week and concentrate on being in Thailand until both plants are being fed that ore from Lotus Halls current mining operation that fills both plants continuously by early April at the latest.
    Surely we get an announcement next week stating Plant#1 has finished construction activities and all parts have undergone dry commissioning.
 