its a very small RC drill program. estimated 2800m for 15-20 holes. a good operator and dependent on the host rock can drill anywhere between 100-250m per day. not considering hiccups with drillrig breakdowns and remobilization etc, it should be just finished or finishing now. say 3000m divided 20 holes, thats 150m per hole
20 holes can be 20 days, add another 10 days for some drill pad set up, water, logistics to camp, unforeseen delays etc etc... 30 days. hence should be done now.
- Forums
- ASX - By Stock
- G11
- General Discussion
General Discussion, page-10
-
- There are more pages in this discussion • 8 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add G11 (ASX) to my watchlist
(20min delay)
|
|||||
Last
1.9¢ |
Change
0.000(0.00%) |
Mkt cap ! $18.36M |
Open | High | Low | Value | Volume |
0.0¢ | 0.0¢ | 0.0¢ | $0 | 0 |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
1 | 167205 | 1.8¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
1.9¢ | 352872 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 167205 | 0.018 |
1 | 30000 | 0.017 |
2 | 219000 | 0.016 |
2 | 1100000 | 0.015 |
1 | 500000 | 0.012 |
Price($) | Vol. | No. |
---|---|---|
0.019 | 352872 | 1 |
0.020 | 450000 | 2 |
0.021 | 850000 | 2 |
0.022 | 800000 | 2 |
0.025 | 15625 | 1 |
Last trade - 16.12pm 18/10/2024 (20 minute delay) ? |
Featured News
G11 (ASX) Chart |
Day chart unavailable