Report estimates 14MW to run the plant, running for 8322hrs (23...

  1. 222 Posts.
    lightbulb Created with Sketch. 68
    Report estimates 14MW to run the plant, running for 8322hrs (23 hrs of the day).
    given the hydro plant is 87km away, assume 10% losses in transmission.
    Implies average load on the hydro plant requires to be about 15MW, leaving about 35MW for other consumption.
    Side note, storage capacity MWhrs state how many hours a 1 MW device can run for. This is very different to rate of consumption (power) MW, 1 000 000 joules consumed every second.
 