Was always wondering how many tonnes of ore were milled in the three months that CGT use in there pre presentations . We know that they milled 104 000 tonnes at 4.3 for the year but I enquired to CGT for the 3 months of September October and November and the results are as follows
Sept 4058 mined and milled tonnes at 10. 6g recovered 9.6g.
Oct 5992 at 9.0 head grade .
Nov 6940 at 7.9 head grade.
Now bear in mind that this was the final cleanup of ore before the sale so i,m presuming anything worth processing went into the mill . So if some low grade was processed as well as good stope ore then some of it must have been going a reasonable amount better than 7-8 and 9 grams.