Hi JohnoThe cost of removing overburden and waste materials to...

  1. 3,559 Posts.


    Hi Johno

    The cost of removing overburden and waste materials to access the ore body at an open pit mine prior to the production phase are referred to as "pre-stripping costs." Pre-stripping costs are capitalized during the development of an open pit mine. Where multiple open pits exist at a mining complex utilizing common processing facilities, pre-stripping costs are capitalized at each pit. The removal, production, and sale of de minimis saleable materials may occur during development and are recorded as Other income, net of incremental mining and processing costs.