Production great, oh yeah? At 3mtpa should do 9,340 tonnes per day, 320 days a year production with 45 days shutdown is industry standard.
Announcement should read:
July another shocker with only just over half of scheduled production. Only 164,000 tonnes throughput of 290,000 scheduled. Sorry we can't put out August because it was a shocker even a lot worse than a July.
Blame the HPGR because it's made in Germany. The real problem was the cheap Chinese Scrubber that caught and the filter presses that collapsed, not the HPGR. These are facts not fiction. Don't want to be blaming the crap Chinese stuff. My guess is that this process plant has no chance of achieving its 3mtpa throughput and putting out untruths like the announcement today is adding fuel to lying fire.
![]()