Some guesstimates on timing:P&A old well and set kick off plugs...

  1. 3,706 Posts.
    lightbulb Created with Sketch. 2852
    Some guesstimates on timing:

    P&A old well and set kick off plugs - 2 days
    Drill circa 1400m sidetrack - 5-7 days depending on ROP. ROP in turn dependent on how much steering they have to do.
    Condition hole and POOH - 1 day
    Run wireline logs - 3-4 days assuming 3-4 runs including RCI/RCX. Last run will most likely be a seismic checkshot survey with that data not required to declare a discovery
    Time to gather and integrate all data - half a day

    Toting up the above comes to a minimum of approximately 12 days.