    Thanks for the post.

    So all going to plan the setup, frac and cleanup should take circa 5 weeks with pumping to start in June - initial flow rates after circa 2 weeks the key (i.e. higher rate the better) and then another circa 8 to 12 weeks before we (hopefully) reach max absorption and one giant mf of a flare...

    Your thoughts? Just trying to re-map the timeline given contractor equipment delays in getting frac underway