Northern Gas Pipeline contractor axed, Jemena to re-tender for...

  1. 10,075 Posts.
    lightbulb Created with Sketch. 4852
    Northern Gas Pipeline contractor axed, Jemena to re-tender for partner
    By Jacqueline Breen
    Posted 11 minutes ago
    Construction of the Northern Gas Pipeline was due to start in April 2017 in Tennant Creek.

    Northern Gas Pipeline start delayed
    The company developing the $800 million gas pipeline that would link Tennant Creek and Mt Isa has terminated its construction deal three weeks after announcing delays resulting from land access problems.
    A spokesman for Jemena said the company had "reviewed arrangements" with contractor McConnell Dowell and determined they "will not meet the needs of the project" that was originally set to start construction in April.
    "This means Jemena will shortly look to appoint construction partners through a competitive tender process," the spokesman said.
    McConnell Dowell was contracted to build the 622-kilometre Northern Gas Pipeline as well as two compressor stations and gas treatment facilities.
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
(20min delay)
Last
5.4¢
Change
0.001(1.89%)
Mkt cap ! $40.24M
Open High Low Value Volume
5.3¢ 5.5¢ 5.2¢ $29.43K 548.4K

Buyers (Bids)

No. Vol. Price($)
1 30496 5.4¢
 

Sellers (Offers)

Price($) Vol. No.
5.6¢ 15000 1
View Market Depth
Last trade - 16.10pm 15/07/2025 (20 minute delay) ?
CTP (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.