    Hi, Sav..Agree totally with you on the GSG and HeN possible scenarios...It will most certainly have to be a multi rig programme if all of the forecast program is to even stand a chance of being met...

    If the programme gets underway, say beginning of March and runs thru to the end of October, then that will afford some 8 months,or approx. 245 days of possible in-the-field working days....

    8 conventional wells at,say, 40 days per well,(includes Mob. and Demob)=320 days..For all sorts of reasons, I would suspect that programme would not total 8 wells, but realistically, something like 6 wells, absolute maximum.(6x40=240),utilizing one Rig..No break-downs!! No downhole problems!! No time for contingencies...


    Now the intriguing part...Some 40 CBM wells are proposed at say,30 days each,(includes Mob.& Demob.),
    = some 1200 drilling days, divide by 245 available field days,= a minimum of 5 CBM rigs...

    That would be a most intensive program in any company's workbook.. The logistics, alone, are mind-boggling...6 Rigs to "baby-sit'and crews to keep happy..Randy will be a busy boy!! Challenging, but possible...














 
watchlist Created with Sketch. Add CTP (ASX) to my watchlist
(20min delay)
Last
4.9¢
Change
0.000(0.00%)
Mkt cap ! $36.26M
Open High Low Value Volume
4.9¢ 4.9¢ 4.8¢ $6.378K 131.3K

Buyers (Bids)

No. Vol. Price($)
3 239074 4.9¢
 

Sellers (Offers)

Price($) Vol. No.
5.0¢ 59455 1
View Market Depth
Last trade - 16.10pm 23/07/2024 (20 minute delay) ?
CTP (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.