re: july production now Annoucement out....June production has become around the end of July.
18 July 2006
AUSTRALIAN STOCK EXCHANGE AND MEDIA RELEASE
INDEE GOLD MINE UPDATE
The company is pleased to provide a further update on progress on the development of the Indee Gold Mine.
• There are now approx 50,000 tonnes of ore on the ROM pad.
• Crushing and agglomeration has commenced with 10,000 tonnes of ore now on the Leach pad.
• Grade control drilling of Withnell North and West pits plus Camel 1 and Camel 2 pits also complete
• An initial gold pour will occur around the end of this month.
Ore Stacking
The following images show the cement silo and agglomerator, and the overland conveyor system which takes the
ore onto the heap leach pads.
The following image shows 10,000 tonnes of ore now stacked on the heap leach pad. The irrigation system will be
installed later this week enabling irrigation to commence.
2
Ponds Commissioning
The pregnant and barren ponds have now been completed and lined, and pump commissioning is underway. The
following image shows the lined barren pond.
Plant construction
The elution plant and gold room have been installed and commissioning is being carried out over the next several
weeks.
Drilling
Grade control drilling at Withnell North, Withnell West, Camel 1 and Camel 2 has been completed. The attached
table provides a summary of some of the more significant results in and around Withnell North open pit received
to date.
- Forums
- ASX - By Stock
- RNG
- june production
june production, page-5
-
- There are more pages in this discussion • 5 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)