just went into prenr, page-4

  1. 219 Posts.
    Apex Minerals NL
    Level 1, 10 Ord Street, West Perth, Western Australia 6005
    PO Box 682 West Perth, Western Australia 6872
    Tel: 61 8 6311 5555 Fax: 61 8 6311 5556 [email protected]
    ASX Code: AXM www.apexminerals.com.au ABN 22 098 612 974
    ASX/MEDIA ANNOUNCEMENT MONDAY 4th MAY, 2009
    Apex Shareholder Update - April Production
    • Targeted commercial gold production achieved in April at 10,000 ounces
    • Plant throughput rate of approximately 850,000 tonnes per annum (above target)
    • Underground ore production 50% higher than previous month to over 40,000 tonnes
    with a grade increase of 15%
    • Gold poured was 9,500 ounces (14% increase from March)
    Overview
    Wiluna achieved a major milestone in April having reached its initial gold production rate target of
    120,000 ounces per annum and as a result commencing commercial production. Accordingly, as of
    1st April, gold sales and operating costs will be shown in the Income and Expenditure statement
    whereas all revenue and expenses up to this date have been capitalised.
    In addition, the company has recently reviewed its manning levels required for ongoing operations
    at Wiluna following the completion of mining in the East Pit open cut and completion of the ramp up
    to steady state operations. As a consequence of this review, the operating workforce at Wiluna has
    been reduced by approximately 30 personnel (or approximately 10% of the operating workforce)
    comprising Apex employees and contract personnel.
    Processing
    The processing plant continued operating well during April with 70,000 tonnes of ore treated at an
    average grade of 5.3 g/t Au (grams gold per tonne), equating to an annualised throughput rate of
    approximately 850,000tpa (tonnes per annum). Monthly plant throughput since January is shown in
    Figure 1.
    Figure 1. Wiluna Monthly Plant Throughput
    Monthly Plant Throughput
    0
    10000
    20000
    30000
    40000
    50000
    60000
    70000
    80000
    January February March April
    Month
    Tonnes
    -
    1.0
    2.0
    3.0
    4.0
    5.0
    6.0
    Grade (g/t Au)
    Tonnes Grade
    2
    The grade of ore treated has continued to improve as the production rate from higher grade
    underground ore sources increases.
    Gold poured in April was 9,500 ounces. Gold production, which includes estimated increase in gold
    in circuit stocks, has increased to Apex’s initial production target of 10,000 ounces per month. Plant
    recovery for April is estimated to be 84%. The Company has undertaken circuit surveys and test
    work that confirm the potential to improve plant throughput, recoveries and costs going forward and
    these are now being pursued.
    Mining
    Open Pit
    Open pit mining continued in East Pit with production of 63,000t @ 4.1 g/t Au being achieved in
    April. Completion of mining activities occurred on 3rd May with the contractor demobilising
    immediately thereafter.
    As detailed in the March quarterly report, most of this ore has been stockpiled on the ROM pad and
    will supplement ongoing underground feed for several months.
    East Lode North Decline
    Preparations have commenced to locate a portal site for the East Lode North underground mine at
    the base of the East Pit following the completion of open pit mining activities. Decline development
    is expected to begin in May. The decline will access an initial reserve of approximately 350,000t @
    5.5 g/t Au situated approximately 300 metres to the north of the expected portal site.
    On its path to the East Lode North orebody the decline will pass alongside mineralisation extending
    immediately below ore recently mined in East Pit. Drives will be developed from the decline to allow
    for close spaced drilling to assess this mineralisation.
    In addition, a drive will be developed to the south of the portal location to allow infill drilling of the
    highly prospective mineralisation intersected in previous drilling immediately below East Pit and
    adjacent to historic workings.
    Underground
    Underground ore production from the Calais zone above the 600RL level was 40,000t @ 5.3 g/t Au
    in April. This represents a 50% increase in tonnes and a 15% increase in grade relative to March’s
    underground production.
    The production rate achieved from the Calais zone above the 600RL level in April equates to an
    annualised rate of approximately 500,000tpa which will be sustained until the new orebodies at
    Henry 5 North, Henry 5, Calais below 600RL and East Lode North have been developed. As a
    result of these developments, the underground production rate is expected to increase to 70,000
    tonnes per month in the second half of 2009. Until then the treatment plant will be supplemented
    with the stockpiled open pit ore.
    Capital decline development towards Henry 5 North has continued and accesses to the first
    production level at the 712RL level commenced at month’s end. Ore driving in the northern end of
    the 712 level is expected to commence in late May with ore driving in the south end expected to
    commence in June. Infill diamond drilling continues to confirm previous resource estimates in the
    area.
    Capital development required to access ore in Calais and Henry 5 below 600RL commenced in
    April. Ore driving on the first stoping levels at approximately 575RL is expected to occur in the
    September quarter.
    Underground ore production since January is shown in Figure 2.
    3
    Figure 2. Wiluna Monthly Underground Production
    Monthly Underground Production
    0
    5,000
    10,000
    15,000
    20,000
    25,000
    30,000
    35,000
    40,000
    45,000
    January February March April
    Month
    Tonnes
    0.0
    1.0
    2.0
    3.0
    4.0
    5.0
    6.0
    Grade (g/t Au)
    Tonnes Grade
    ROM and Developed Ore Stocks
    ROM stocks at the end of April were 253,000t @ 3.3 g/t Au. Ore remaining in stopes in production
    or already developed in Calais above 600RL is 165,000t @ 6.0 g/t Au. The combination of ROM
    and underground developed stocks is 420,000t @ 4.4 g/t Au for a total of approximately 59,000
    ounces of contained gold.
    tonnes x g/t Au Au (oz)
    Developed Underground
    Calais Stopes above 600mRL 165,000 @ 6.0 31,800
    ROM Stocks
    Open Pit – medium grade 182,000 @ 3.8 22,300
    Open Pit – low grade 71,000 @ 2.2 5,000
    Sub-Total 253,000 @ 3.3 27,300
    Total 420,000 @ 4.4 59,100
    Mark Ashley
    CEO and managing Director
    Contact: Mark Ashley Ph: +61 8 6311 5555 Mobile: 0411 470 104
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.