Abilene, Texas data centre in the USSA
substation first built May 2022
crusoe began construction June 2024
crusoe founder interview says relationship with owner started with the substation in place.
so say maybe 1 to 2 years from introduction to construction. Even that is quick.
so when was Crusoe founder first introduced to KDP man-agers?
say mid 2024
so if construction is to begin 2 years later, that's mid 2026.
timeline is stretching out
but still within bounds of a major project or 3
somehow the regulator may have sped things up
meanwhile, since MOU:
AESO regulations were changing and have changed.
political ruling class had a selection staged in US, Canada, and Australia (all red and blue which combines to make royal purple)
- Forums
- ASX - By Stock
- KPO
- KPO related news stories
KPO
kalina power limited
Add to My Watchlist
20.0%
!
0.4¢

KPO related news stories, page-381
Featured News
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
|
|||||
Last
0.4¢ |
Change
-0.001(20.0%) |
Mkt cap ! $11.73M |
Open | High | Low | Value | Volume |
0.5¢ | 0.5¢ | 0.4¢ | $35.4K | 7.946M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
2 | 2500000 | 0.4¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
0.5¢ | 3151849 | 7 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
2 | 2500000 | 0.004 |
10 | 8066119 | 0.003 |
4 | 900033 | 0.002 |
2 | 2100024 | 0.001 |
0 | 0 | 0.000 |
Price($) | Vol. | No. |
---|---|---|
0.005 | 3151849 | 7 |
0.006 | 1194356 | 6 |
0.007 | 668502 | 4 |
0.008 | 2785000 | 3 |
0.010 | 87500 | 2 |
Last trade - 15.58pm 25/06/2025 (20 minute delay) ? |
Featured News
KPO (ASX) Chart |