timmo,
"Testing is successful, its operational."
I think you are getting a bit ahead of yourself.
Last Qrtly Ann:
Construction 100% complete (although they go on to describe site construction workforce stood at 289 completing miscellaneous site works and providing support for commissioning activities) So now that miscellaneous site works has finished, CONSTRUCTION 100%.
Pre Commissioning 99% complete (77 out of 85 systems handed over for commissioning) Completion of this may or may not be included in construction completion.
Commissioning 64% complete
My understanding is that concentrate is needed for completion of commissioning. Something that will only happen when TOL is issued.
Happy to be proven wrong.
- Forums
- ASX - By Stock
- LYC
- kuantan residents allowed to challenge tol,,,,
kuantan residents allowed to challenge tol,,,,, page-16
-
- There are more pages in this discussion • 32 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add LYC (ASX) to my watchlist
(20min delay)
|
|||||
Last
$7.34 |
Change
-0.260(3.42%) |
Mkt cap ! $6.860B |
Open | High | Low | Value | Volume |
$7.55 | $7.56 | $7.30 | $32.37M | 4.384M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
1 | 84497 | $7.34 |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
$7.35 | 23514 | 2 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 84497 | 7.340 |
1 | 2318 | 7.310 |
1 | 1720 | 7.290 |
5 | 15815 | 7.280 |
3 | 48516 | 7.270 |
Price($) | Vol. | No. |
---|---|---|
7.360 | 9683 | 1 |
7.370 | 9683 | 1 |
7.380 | 9683 | 1 |
7.400 | 9683 | 1 |
7.420 | 10955 | 2 |
Last trade - 16.10pm 14/11/2024 (20 minute delay) ? |
Featured News
LYC (ASX) Chart |