    Certainly endorse that.

    Could I also query the 60 days assumption which I have seen made on these threads.

    My read is the Dry plant is now in early production.

    Adam confirmed the Wet plant has now commenced commissioning.

    The 85% was a measure as at 31 March, that is almost 5 weeks ago. And we know that construction activities then outstanding included the paste plant for UG, and for the remaining wind turbines. None of that is critical path to first production, I assume, given we have tonnes of rock on standby and other power sources.

    I would not be surprised if first spod emerged sooner than 60 days!.
 
watchlist Created with Sketch. Add LTR (ASX) to my watchlist
(20min delay)
Last
$1.16
Change
-0.020(1.69%)
Mkt cap ! $2.812B
Open High Low Value Volume
$1.19 $1.19 $1.16 $15.36M 13.12M

Buyers (Bids)

No. Vol. Price($)
18 147576 $1.16
 

Sellers (Offers)

Price($) Vol. No.
$1.17 85567 3
View Market Depth
Last trade - 16.10pm 07/06/2024 (20 minute delay) ?
Last
$1.16
  Change
-0.020 ( 2.13 %)
Open High Low Volume
$1.19 $1.19 $1.16 2578713
Last updated 15.59pm 07/06/2024 ?
LTR (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.