This is from the announcement "BUENA VISTA IRON PROJECT - FINANCING UPDATE" on 17/11/2011
"High quality magnetite concentrate is scheduled to be available for shipping within 9-12 months of finalising Project finance."
CHAIRMAN’S ADDRESS from 24/11/11
"Our team advise that Buena Vista will be capable of commissioning within 12 months of finance being secured. Whilst that now suggests a target of the March quarter 2013 for the commencement of production"
Now on the website which seems new
" In conjunction with an active programme to secure the remaining mining and environmental permits Richmond anticipates that production will commence within 12-15 months of the securing of final finance. At this stage the first half of calendar 2013 is the targeted date for the commencement of production."
So originally we will be shipping high grade ore 9-12 months from financing, to it being commissioned (my understanding of that word is the the mine will start) from 12 months of financing, to production will commence 12-15 months from finance. This is starting to get me worried!
- Forums
- ASX - By Stock
- lack of information? or sneaky?
This is from the announcement "BUENA VISTA IRON PROJECT -...
-
- There are more pages in this discussion • 3 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add RHM (ASX) to my watchlist
Currently unlisted public company.
The Watchlist
FHE
FRONTIER ENERGY LIMITED
Adam Kiley, CEO
Adam Kiley
CEO
SPONSORED BY The Market Online