A very simple rule of thumb which I typically use when evaluating timeframes (my background is large construction projects) is that a best case scenario is for a company to spend an average of $1M day on construction activities. Then add additional time for feasibility studies, engineering (50-100% of the construction timeframe)
Therefore applying this to other projects results in the following:
* Arafura - BFS complete end of 2012
- Allow 6 months decision to mine, contracting, financing etc (ambitious but doable if they get their ducks lined up - June 2013
- ~$1B costs - Lets assume 80% of these are direct construction. Therefore 800 days construction - 2 years Therefore assume min 1yr engineering - June 2014
- 2 years construction and you get to the mid-2016 before commissioning and operation, assuming everything goes well and you don't have any delays. To me 2017 would be more likely.
* Alkane - BFS complete end of 2011 (being conservative from their recent announcements)
- Allow 6 months financing etc - June 2012
- ~$500M costs (until they confirm throughput this is just a guess). Assuming $400M relate to construction or 1 1/2 years. I year engineering - June 2013
- 1 1/2 years construction - end 2014
Chihawk can update on Moly, but assuming assuming a $600M capital spend they are still looking at about 2 years construction, when they have finished their engineering to an acceptable level, and who knows when this is.
- Forums
- ASX - By Stock
- LYC
- lamp
lamp, page-3
-
- There are more pages in this discussion • 2 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
STX
Strike hands $48.5M contract to Clarke Energy to produce 20x 4.5MW gas engines for Sth Erregulla
MND
Albemarle lithium downsize burns $200M hole in Monadelphous's pocket as latter's contracts terminated
Add LYC (ASX) to my watchlist
|
|||||
Last
$6.13 |
Change
-0.165(2.62%) |
Mkt cap ! $5.729B |
Open | High | Low | Value | Volume |
$6.12 | $6.15 | $6.09 | $5.461M | 892.1K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
29 | 14244 | $6.12 |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
$6.13 | 12553 | 22 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
29 | 14244 | 6.120 |
22 | 20673 | 6.110 |
25 | 59566 | 6.100 |
13 | 34020 | 6.090 |
16 | 117298 | 6.080 |
Price($) | Vol. | No. |
---|---|---|
6.130 | 12960 | 22 |
6.140 | 45770 | 22 |
6.150 | 50374 | 15 |
6.160 | 89853 | 10 |
6.170 | 10519 | 7 |
Last trade - 11.48am 02/08/2024 (20 minute delay) ? |
Featured News
TG1
TechGen Metals kicks off airborne geophys survey at Sally Downs copper play – a first for the permit
GML
Gateway Mining sells WA Eastern Montague gold project to Brightstar for $14M – half of that in shares
LYC (ASX) Chart |