Sorted a few gold companies with projects at feasibility or finance/contruction phase with similar ball park stats to LAT to compare values against peers. Not a complete list at all just a few i can think of.
LAT has been discounted largely due to significant difficulties obtaining local permits in Peru for exploration and development but was awarded pre-development permits in July this year, the mining permit is still a key hurdle.
Company also disclosed that it had received unsolicited
approaches to invest in the project/company which were declined. Still a roughy but summary below gives a few ideas where LAT sits in terms of EV and capex/opex profile. Also backs up my comments on KGL.
LAT
Stage Feasibility
EV ~A$11M
Resources 6.2 Mt @ 1.7 Au eq
Capex US$30M (inc owner equipment and possible reduction in site location costs?)
Production 44 kozpa Au Eq
Cash Costs US$223/oz
Grade 1.6 g/t Au
Mine life 6 years
Capex Intensity ~US$682/oz
YTC (Hera)
Stage Feasibility
EV A$50M
Resources 1.8Mt @ 8.8 Au eq
Capex US$51M
Production 46kozpa Au Eq
Cash Costs A$360/oz
Mine life +7 years
Capex Intensity ~US$1109/oz
TRY (Casposo)
Stage Finance/Construction
EV A$144M
Resources 2.4Mt @ 7.9 Au eq
Capex US$74.5M (inc IAU payment)
Production 67kozpa Au Eq (higher with lower gold silver ratio)
Cash Costs US$90/oz Au Eq (likely lower or negative with silver)
Mine life 6 years
Capex Intensity ~US$1112/oz
KGL
Stage Finance
EV A$27M
Resources 19.2Mt @ 1.8 Au eq
Capex US$70.4M
Production 87 kozpa Au Eq
Cash Costs US$0/oz Au Eq (copper credits)
Mine life +8 years
Capex Intensity ~US$809/oz
KRM (Way Linggo)
Stage Construction
EV A$143M
Resources 0.67Mt @ 10.6 Au eq
Capex US$24M
Production 58 kozpa Au Eq (possibly higher from recent UG development)
Cash Costs US$143/oz Au Eq (silver credits)
Mine life +4 years
Capex Intensity ~US$414/oz
EVG (las lagunas)
Stage Finance
EV A$28M
Resources 5.1Mt @ 4.4 Au eq
Capex US$72.5M
Production 75 kozpa Au Eq
Cash Costs US$333/oz Au Eq (silver credits)
Mine life +6 years
Capex Intensity ~US$967/oz
RED (Siana)
Stage Finance
EV A$70M
Resources 5.1Mt @ 4.5 Au eq
Capex US$72.5M
Production 85 kozpa Au Eq
Cash Costs US$351/oz Au Eq
Mine life 10 years
Capex Intensity ~US$967/oz
- Forums
- ASX - By Stock
- latin gold feasibility comparison
LAT
latitude 66 limited
Add to My Watchlist
0.00%
!
4.3¢

Sorted a few gold companies with projects at feasibility or...
Featured News
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
|
|||||
Last
4.3¢ |
Change
0.000(0.00%) |
Mkt cap ! $6.166M |
Open | High | Low | Value | Volume |
4.3¢ | 4.3¢ | 4.3¢ | $172 | 4K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
1 | 19673 | 4.3¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
4.5¢ | 19353 | 3 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 19673 | 0.043 |
1 | 22665 | 0.042 |
1 | 126193 | 0.040 |
1 | 35665 | 0.037 |
1 | 16500 | 0.035 |
Price($) | Vol. | No. |
---|---|---|
0.045 | 19353 | 3 |
0.047 | 30054 | 1 |
0.048 | 52000 | 1 |
0.049 | 3750 | 1 |
0.050 | 20115 | 2 |
Last trade - 10.22am 01/08/2025 (20 minute delay) ? |
Featured News
LAT (ASX) Chart |