Some infos on AGO Ridley Magnetite Project (AGO Ann 14 April...

  1. 1,195 Posts.
    lightbulb Created with Sketch. 2
    Some infos on AGO Ridley Magnetite Project (AGO Ann 14 April 2009, and PFS):

    - Only 75km from Port Hedland, adjacent to Pardoo...Infrastructure in close proximity to the declared Goldsworthy Railway. ...Export alternatives include South West Creek, Anketell and trans-shipping.

    - In-situ resource = 2 billions tonnes @ 36.5% Fe.
    - Reserve of 970Mt at 36%Fe1, DTR grade of 68.3%Fe & 3.8% SiO2, recovery = 37.2%
    - Mine life >20yrs, potential to 35yrs, 15Mtpa at $A36/t Opex, $A2.7Bn Capex

    Points to note
    1. DTR grade show a good concentrate product (+68%Fe), quality slightly higher than Mt Bevan (+67%Fe)

    2. Cash cost of AGO Ridley Magnetite Project looks better than JMS Mt IDA magnetite project:

    AGO Ridley = A$36.22/tonne of concentrate, or A$12.64/tonne of ore mined.

    JMS Mt IDA magnetite project = $62.78 per tonne of magnetite concentrate produced (based on JMS figure scoping studing and also PFS)

    3. JMS Mt IDA magnetite project is commercially viable, as scoping study showed it generates an NPV of $1,685 million @ an 8 % pa discount rate, and an IRR of 19.8% pa.

    DCF valuations for LCY Mt Bevan project
    Using JMS's scoping study for base case scenario, my DCF modeling for LCY Mt Bevan showed the project is viable with an IRR = 25%, using a conservative FOB price for concentrate = US$110/t, well below the current spot FOB Iron Fines Price of US$173.66/dmt for West Australia 62% Fe...

    Also Operating costs could be reduced based on the latest DTR tests..

    http://hotcopper.com.au/post_single.asp?fid=1&tid=1432082&msgid=8131726

    So just for fun, I try to do some DCF valuations for LCY using JMS's scoping study for base case scenario:

    Assumptions:
    - JORC 1.1 to 1.3b tonnes magnetite @ 30 - 40% Fe
    - Capex = $1,582m
    - Cash cost = $62.78/t
    - FOB price for concentrate = US$110/t
    - Royalty = 5%
    - LOM = 20 years
    - Production = 10Mtpa

    - Parity US/AUD = 1

    LCY has 60% stake in the project.

    Notes:
    - Capex is based on the magnetite concentrator at Mt Ida with the concentrate pumped to a filter and dewatering plant located at a rail head at Menzies.

    - Based on LOM = 20 years @ 25Mtpa, producing 10Mtpa of Magnetite Concentrate.

    - Cash cost include Mining/Crushing, Concentrator, transports, port, admin, etc...

    - Royalty of 5%, equity funding and ignoring taxation

    - FOB Concentrate price = US$110/t

    I came up with the following DCF results for LCY:

    Result1
    Assume LCY has got 500 millions shares on issues (currently LCY has 263 millions).

    --> NPV @ 8% per share = $0.36
    --> When production: NPV per share = $4.61 (using zero discount).

    Result2
    Using full Equity with no taxes (JMS assumptions)

    - Capex of $1,582m will require 4,395 millions shares (using NPV per share of $0.36)

    - Total shares on issue = 4,395m + 500m = 4,895m

    --> NPV @ 8% per share = $0.36

    --> When production:
    ---->NPV per share = $1.03 (using zero discount)
    ---->With P/E = 4, NPV @ 8% per share = $1.80

    --> Project IRR = 25%


    Also more infos:

    1. GBG for its Karara magnetite project: Magnetite vs Hematite.

    http://www.gindalbie.com.au/Our+Projects/Magnetite+vs.+Hematite/default.aspx

    2. Lower costs boost Hawsons value to $3.2Bn: Project NPV up 14% to $3.2 billion and IRR rises to 23%

    http://www.carpentariaex.com.au/Files/646535Lower_costs_boost_Hawsons_value_to_$3.2Bn.pdf

    3. Spot price of FOB Iron Fines Price:

    Latest Indian Iron Ore Fines Price - FOB (April 2011)
    Fe 63.5/63% = US$170

    ...Also the Indian government raised the tax on iron ore exports to 20% for fines and lumps (previously 5% for iron ore fines and 15% for lumps) with effect from 1 March, 2011

    http://himadrin.blogspot.com.au/2011/04/latest-indian-iron-ore-fines-price-fob.html


    TSI Iron Ore Spot Reference Prices (US$/dry metric tonne)
    Indicative FOB Spot Prices (US$/dry metric tonne):

    Using TSI’s 62% Fe, 2% Al series, indicative Q2 contract prices are as follows: FOB West Australia 62% Fe at US$173.66/dmt

    http://www.thesteelindex.com/files/custom/TSI%20iron%20ore%20monthly%20review%20-%20February%202011%20revision.pdf


    DYOR,

    Cheers,
 
watchlist Created with Sketch. Add LCY (ASX) to my watchlist
(20min delay)
Last
1.7¢
Change
0.000(0.00%)
Mkt cap ! $131.1M
Open High Low Value Volume
1.7¢ 1.7¢ 1.6¢ $4.365K 271.0K

Buyers (Bids)

No. Vol. Price($)
1 20570 1.6¢
 

Sellers (Offers)

Price($) Vol. No.
1.7¢ 349448 1
View Market Depth
Last trade - 15.51pm 02/08/2024 (20 minute delay) ?
LCY (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.