Thanks for the responses but none of those points answer my key question... I'm fully aware of the AIDEA status for this road, hence my questions on this critical infrastructure.
My question is how dependant is Nova on this road being built in order to build the processing plant system and therefore begin production, or can it be done using the snow road and air drop? I agree with the view that the WSAR will be a PPP and users will be required to pay a toll of sorts.
- Forums
- ASX - By Stock
- NVA
- Livengood Gold PFS
Livengood Gold PFS, page-66
-
- There are more pages in this discussion • 5 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
KAI
Pilbara Minerals buys land off Kairos part of its York gold project for $20M – and a 2% royalty on any PLS gold sales
TG1
TechGen Metals kicks off airborne geophys survey at Sally Downs copper play – a first for the permit
STX
Strike hands $48.5M contract to Clarke Energy to produce 20x 4.5MW gas engines for Sth Erregulla
Add NVA (ASX) to my watchlist
|
|||||
Last
13.5¢ |
Change
-0.005(3.57%) |
Mkt cap ! $32.88M |
Open | High | Low | Value | Volume |
13.5¢ | 14.0¢ | 13.5¢ | $34.92K | 257.6K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
2 | 15661 | 13.5¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
14.0¢ | 30000 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
2 | 15661 | 0.135 |
6 | 143803 | 0.130 |
3 | 166600 | 0.125 |
5 | 173169 | 0.120 |
5 | 150490 | 0.115 |
Price($) | Vol. | No. |
---|---|---|
0.145 | 15000 | 1 |
0.150 | 10000 | 1 |
0.160 | 50000 | 1 |
0.165 | 99341 | 2 |
0.170 | 35000 | 1 |
Last trade - 16.10pm 02/08/2024 (20 minute delay) ? |
Featured News
NVA (ASX) Chart |