LKE 0.00% 3.4¢ lake resources n.l.

There appears (on the face of it) to be some confusion with the...

  1. 16,761 Posts.
    lightbulb Created with Sketch. 2612
    There appears (on the face of it) to be some confusion with the use of words like..."in"...&..."end" with respect to LKE timelines and slippage.

    For example:

    On 30 July 2021, LKE stated:
    "Definitive Feasibility Study (DFS) continues for Kachi with Hatch as lead consultant, with completion anticipated in Q1 2022."

    Then 11 AUG 2021 states:
    "The DFS and ESIA are well advanced, targeting completion by the end of Q1, 2022."

    That's generally regarded as slippage.

    I note Demo plant timeline stated 16 JULY 2021 as "Q4, 2021", which starts in 2.5 weeks:
    https://hotcopper.com.au/data/attachments/3566/3566792-3a48cd1b25d134f56971fdb31d7e775d.jpg
 
watchlist Created with Sketch. Add LKE (ASX) to my watchlist
(20min delay)
Last
3.4¢
Change
0.000(0.00%)
Mkt cap ! $56.72M
Open High Low Value Volume
3.5¢ 3.5¢ 3.4¢ $58.86K 1.714M

Buyers (Bids)

No. Vol. Price($)
13 1317660 3.4¢
 

Sellers (Offers)

Price($) Vol. No.
3.5¢ 259343 3
View Market Depth
Last trade - 16.10pm 09/08/2024 (20 minute delay) ?
LKE (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.