Best timeline I'd guess, post EPA/Ministerial approval:
Formal offtakes 3-6 months
Finance +3mnths after offtakes
Final design and procure, confirmed transport/port contracts, etc in parallel with offtakes and finance, ready for signing
->DFS/FID
Completed production trials and optimisation, recruitment
Production start-up 3-6 mnths
=> prodn in 12-15 mnths from Ministerial approval
The last presso said construction in 6-8mnths from final approvals.
I'd include EPA/Minister/offtakes/finance/final DFS/FID all complete as "approvals" before that 6-8months starts, so consistent with the above
rerates with
approval
offtakes
finance
FID
prodn/cashflow and ramp up
Muchea progress
- Forums
- ASX - By Stock
- VRX
- Long suffering holder
Long suffering holder, page-177
-
- There are more pages in this discussion • 55 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add VRX (ASX) to my watchlist
|
|||||
Last
3.4¢ |
Change
-0.005(12.8%) |
Mkt cap ! $21.36M |
Open | High | Low | Value | Volume |
3.7¢ | 3.7¢ | 3.4¢ | $5.444K | 152.5K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
7 | 302744 | 3.4¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
3.9¢ | 39999 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
7 | 302744 | 0.034 |
3 | 927637 | 0.033 |
2 | 225000 | 0.032 |
1 | 302425 | 0.031 |
3 | 303376 | 0.030 |
Price($) | Vol. | No. |
---|---|---|
0.039 | 39999 | 1 |
0.040 | 160911 | 3 |
0.042 | 171626 | 2 |
0.043 | 28768 | 1 |
0.046 | 27010 | 1 |
Last trade - 12.09pm 03/07/2024 (20 minute delay) ? |
Featured News
VRX (ASX) Chart |
The Watchlist
TON
TRITON MINERALS LTD
Adrian Costello, Executive Director
Adrian Costello
Executive Director
Previous Video
Next Video
SPONSORED BY The Market Online