    Best timeline I'd guess, post EPA/Ministerial approval:

    Formal offtakes 3-6 months
    Finance +3mnths after offtakes
    Final design and procure, confirmed transport/port contracts, etc in parallel with offtakes and finance, ready for signing
    ->DFS/FID
    Completed production trials and optimisation, recruitment
    Production start-up 3-6 mnths

    => prodn in 12-15 mnths from Ministerial approval

    The last presso said construction in 6-8mnths from final approvals.
    I'd include EPA/Minister/offtakes/finance/final DFS/FID all complete as "approvals" before that 6-8months starts, so consistent with the above

    rerates with
    approval
    offtakes
    finance
    FID
    prodn/cashflow and ramp up
    Muchea progress
 