Best timeline I'd guess, post EPA/Ministerial approval:
Formal offtakes 3-6 months
Finance +3mnths after offtakes
Final design and procure, confirmed transport/port contracts, etc in parallel with offtakes and finance, ready for signing
->DFS/FID
Completed production trials and optimisation, recruitment
Production start-up 3-6 mnths
=> prodn in 12-15 mnths from Ministerial approval
The last presso said construction in 6-8mnths from final approvals.
I'd include EPA/Minister/offtakes/finance/final DFS/FID all complete as "approvals" before that 6-8months starts, so consistent with the above
rerates with
approval
offtakes
finance
FID
prodn/cashflow and ramp up
Muchea progress
- Forums
- ASX - By Stock
- VRX
- Long suffering holder
Long suffering holder, page-177
-
- There are more pages in this discussion • 170 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add VRX (ASX) to my watchlist
(20min delay)
|
|||||
Last
3.4¢ |
Change
0.000(0.00%) |
Mkt cap ! $21.36M |
Open | High | Low | Value | Volume |
3.4¢ | 3.5¢ | 3.1¢ | $8.239K | 237.4K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
2 | 109108 | 3.2¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
3.5¢ | 272929 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
2 | 109108 | 0.032 |
3 | 218235 | 0.031 |
1 | 33330 | 0.030 |
3 | 440647 | 0.028 |
7 | 754262 | 0.027 |
Price($) | Vol. | No. |
---|---|---|
0.035 | 272929 | 1 |
0.039 | 14571 | 1 |
0.040 | 54011 | 1 |
0.041 | 38235 | 1 |
0.042 | 328937 | 3 |
Last trade - 15.58pm 02/10/2024 (20 minute delay) ? |
Featured News
VRX (ASX) Chart |