VRX 5.56% 3.8¢ vrx silica limited

Long suffering holder, page-177

  1. 10,615 Posts.
    lightbulb Created with Sketch. 224
    Best timeline I'd guess, post EPA/Ministerial approval:

    Formal offtakes 3-6 months
    Finance +3mnths after offtakes
    Final design and procure, confirmed transport/port contracts, etc in parallel with offtakes and finance, ready for signing
    ->DFS/FID
    Completed production trials and optimisation, recruitment
    Production start-up 3-6 mnths

    => prodn in 12-15 mnths from Ministerial approval

    The last presso said construction in 6-8mnths from final approvals.
    I'd include EPA/Minister/offtakes/finance/final DFS/FID all complete as "approvals" before that 6-8months starts, so consistent with the above

    rerates with
    approval
    offtakes
    finance
    FID
    prodn/cashflow and ramp up
    Muchea progress
 
watchlist Created with Sketch. Add VRX (ASX) to my watchlist
(20min delay)
Last
3.8¢
Change
0.002(5.56%)
Mkt cap ! $23.87M
Open High Low Value Volume
3.7¢ 3.8¢ 3.2¢ $52.59K 1.528M

Buyers (Bids)

No. Vol. Price($)
1 134997 3.6¢
 

Sellers (Offers)

Price($) Vol. No.
3.8¢ 18126 1
View Market Depth
Last trade - 15.56pm 28/06/2024 (20 minute delay) ?
VRX (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.