. Jiangsu project completion and commissioning staged over next five months . Overall project is 76% complete . Construction labour deficiency in China has contributed to revised schedule . Back half of Jiangsu plant to complete with commissioning to commence during Q3 2011 . Front half of the plant to complete with commissioning to commence during Q4 2011 . Capital budget increased by 36% in A$ terms to A$99.8m (RMB 689 million) . No requirement to raise further funds