Your order of operations is absolutely correct as per PFC Ann. on 9 July,2012.
Best that posters brush up on FACTS by referring to the link for the PFC story:-
http://tmx.quotemedia.com/article.php?newsid=52577017&qm_symbol=PFC
Also note that the DRILLING of O-3H ' is expected to take 4 to 5 weeks'.
So, 9 July + 5 weeks = say 16 August for completion of drilling (only).
MacIntyre-2 is the first to be fracced. As the (Halliburton) 'fracc spread' equipment for this operation is completly different to drilling, they may already be on site (before completion of DRILLING of O-3H is finalised.
They (HB) may only have to wait for the Operator to return to the M-2 site for supervision/coordination before they can commence, i.e., there may not be a further wait from 16 August.
Either way, certainly getting close
zacan..
The BKP Ann. of 9 July - 2nd para - staes that the completion programmr will be ready for commencement (NOT completion) in approx 3-4 weeks, subject to notification by the opertors (PFC?Statoil presumeably)
- Forums
- ASX - By Stock
- CND
- macintyre 2h fracing
macintyre 2h fracing, page-5
-
- There are more pages in this discussion • 14 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add CND (ASX) to my watchlist
(20min delay)
|
|||||
Last
3.2¢ |
Change
0.001(3.23%) |
Mkt cap ! $18.60M |
Open | High | Low | Value | Volume |
3.1¢ | 3.2¢ | 3.1¢ | $7.055K | 226.6K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
3 | 191746 | 3.1¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
3.4¢ | 97587 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
3 | 191746 | 0.031 |
2 | 150000 | 0.030 |
1 | 200000 | 0.029 |
2 | 273000 | 0.028 |
3 | 367185 | 0.027 |
Price($) | Vol. | No. |
---|---|---|
0.034 | 97587 | 1 |
0.035 | 224200 | 3 |
0.036 | 197219 | 5 |
0.037 | 100000 | 1 |
0.038 | 100000 | 1 |
Last trade - 13.14pm 08/10/2024 (20 minute delay) ? |
Featured News
CND (ASX) Chart |