Stage 1 is what is happening now - I know. It will take 2.5-3 yrs to build and 2-2.5yrs to ramp if you have enough graphite. The build site is currently shutdown over winter and there is always delays.
Appeals have pushed this out somewhat, but it certainly will not take 6 years to get up and running - you stated it won't reach nameplate until the end of 2030. Which means TLG won't achieve your projected EBITDA of $260m AUD annually until 2031.
It's logical to ramp the mine at the same rate as the AAM plant. The hard part is building the concentrator plant and dialling it in. NextSource just had problems at their Molo mine with their plant. It's 17ktpa and TLG's will be 22ktpa. You can imagine the problems SYR had with their 350ktpa plant
- Forums
- ASX - By Stock
- Media Reports
Stage 1 is what is happening now - I know. It will take 2.5-3...
-
- There are more pages in this discussion • 131 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add SYR (ASX) to my watchlist
(20min delay)
|
|||||
Last
26.5¢ |
Change
-0.010(3.64%) |
Mkt cap ! $274.2M |
Open | High | Low | Value | Volume |
28.0¢ | 28.0¢ | 26.5¢ | $966.4K | 3.568M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
17 | 548863 | 26.5¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
27.0¢ | 128000 | 2 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
13 | 516752 | 0.265 |
14 | 635653 | 0.260 |
11 | 614692 | 0.255 |
26 | 667586 | 0.250 |
12 | 697154 | 0.245 |
Price($) | Vol. | No. |
---|---|---|
0.270 | 128000 | 2 |
0.275 | 138231 | 5 |
0.280 | 100439 | 6 |
0.285 | 186430 | 4 |
0.290 | 178000 | 7 |
Last trade - 16.10pm 08/11/2024 (20 minute delay) ? |
Featured News
SYR (ASX) Chart |
The Watchlist
EQN
EQUINOX RESOURCES LIMITED.
Zac Komur, MD & CEO
Zac Komur
MD & CEO
SPONSORED BY The Market Online