Three weeks to go and going off the Rising Stars presentation....

  1. 449 Posts.
    lightbulb Created with Sketch. 183
    Three weeks to go and going off the Rising Stars presentation. TNG staff must be sleeping in the offices at the moment???....


    Be good to see the Chair and CEO names on an update with respect to these timeframes from the 14/2/22 ASX Announcement???

    "2022 MOUNT PEAKE PROJECT ACTIVITIES – INDICATIVE TARGETED TIMING

    Activity Indicative targeted timing

    Completion of value engineering and design by Clough Jun 22 Quarter
    Delivery of an updated capital cost estimate for the integrated Mount Peake Project Jun 22 Quarter
    Completion of borefield drilling program and application for water extraction licence Jun 22 Quarter
    Completion of review of NPI items for tendering process Jun 22 Quarter."

 