Am afraid I am sceptical with the true situation on site.
To treble the electrical and piping tradesmen numbers last month smacks to me of poor site management such that they only just realised they needed a huge increase in work effort. The same goes for the mechanical trades.
I would also like to know also why the Grid power is not yet connected - being cynical, maybe they want to again blame the Authority for late power supply!
Note also they need to have the piping completed before they can truly start the commissioning program.
All this last minute stuff is no way to start up a big project. Westmoon